T/F: Risks can have both negative and positive effects on meeting project objectives. - 
answerTrue 
T/F: One possible response to managing negative risk it to accept the potential effects from the 
risk. - answerTrue 
T/F: A risk-seeking person prefers ou...
Voorbeeld 2 van de 5 pagina's
In winkelwagenITPM FINAL EXAM QUESTIONS & 
ANSWERS, 2024 
T/F: Risks can have both negative and positive effects on meeting project objectives. - 
answerTrue 
T/F: One possible response to managing negative risk it to accept the potential effects from the 
risk. - answerTrue 
T/F: A risk-seeking person prefers ou...
IST 301 Exam 2 ITPM/EA Questions with 
100% Correct Answers 
What are the three pervasive problems with IT projects? - answerLate delivery, overbudget, 
does not meet business requirements 
What is IT portfolio management - answerManaging IT as a portfolio of assets like a 
financial portfolio 
What...
Voorbeeld 1 van de 2 pagina's
In winkelwagenIST 301 Exam 2 ITPM/EA Questions with 
100% Correct Answers 
What are the three pervasive problems with IT projects? - answerLate delivery, overbudget, 
does not meet business requirements 
What is IT portfolio management - answerManaging IT as a portfolio of assets like a 
financial portfolio 
What...
ITPM Exam 1 Review Questions with 
100% Correct Answers 
We need to reduce delays in our system. 
Explicit (E) 
Implicit (I) - answerExplicit (E) 
Is it hard to recruit skilled people? 
Problem (P) 
Situation (S) - answerProblem (P) 
Have these staffing problems led you to lose customers? 
Implicati...
Voorbeeld 2 van de 6 pagina's
In winkelwagenITPM Exam 1 Review Questions with 
100% Correct Answers 
We need to reduce delays in our system. 
Explicit (E) 
Implicit (I) - answerExplicit (E) 
Is it hard to recruit skilled people? 
Problem (P) 
Situation (S) - answerProblem (P) 
Have these staffing problems led you to lose customers? 
Implicati...
ITPM Chapter 6 Exam 2 Questions with 
100% Correct Answers 
In project schedule management, which process primarily involves checking and managing 
changes to the project schedule? 
A. estimating activity durations 
B. developing the schedule 
C. controlling the schedule 
D. estimating activity reso...
Voorbeeld 1 van de 3 pagina's
In winkelwagenITPM Chapter 6 Exam 2 Questions with 
100% Correct Answers 
In project schedule management, which process primarily involves checking and managing 
changes to the project schedule? 
A. estimating activity durations 
B. developing the schedule 
C. controlling the schedule 
D. estimating activity reso...
ITPM Chapter 5 Exam 2 ISDS Questions 
And Answers 100% Verified 2024 
Which term describes a product produced as part of a project? 
A. variance 
B. scope 
C. deliverable 
D. work package - answerC. deliverable 
Which statement best describes scope? 
A. each level of work that is outlined in a work ...
Voorbeeld 1 van de 3 pagina's
In winkelwagenITPM Chapter 5 Exam 2 ISDS Questions 
And Answers 100% Verified 2024 
Which term describes a product produced as part of a project? 
A. variance 
B. scope 
C. deliverable 
D. work package - answerC. deliverable 
Which statement best describes scope? 
A. each level of work that is outlined in a work ...
ITPM Exam 3 Ch.8 Questions And 
Answers 100% Verified 2024 
What is Project Quality Management? - answerEnsures that the project will satisfy the needs 
for which it was undertaken 
What are the process for Project Quality Management? - answer-Planning quality 
management 
-Performing quality manage...
Voorbeeld 1 van de 4 pagina's
In winkelwagenITPM Exam 3 Ch.8 Questions And 
Answers 100% Verified 2024 
What is Project Quality Management? - answerEnsures that the project will satisfy the needs 
for which it was undertaken 
What are the process for Project Quality Management? - answer-Planning quality 
management 
-Performing quality manage...
IST 301 - Exam 2 ITPM Questions And 
Answers 100% Verified 2024 
What are the three pervasive problems with IT projects? - answerLate delivery, overbudget, 
does not meet business requirements 
What is the relationship between corporate strategy and IT investments? - 
answerInvestments in IT should ...
Voorbeeld 1 van de 2 pagina's
In winkelwagenIST 301 - Exam 2 ITPM Questions And 
Answers 100% Verified 2024 
What are the three pervasive problems with IT projects? - answerLate delivery, overbudget, 
does not meet business requirements 
What is the relationship between corporate strategy and IT investments? - 
answerInvestments in IT should ...
ITPM Chapter 4 Exam 2 Questions And 
Answers 100% Verified 2024 
Which process involves working with stakeholders to create the document that formally 
authorizes a project? 
A. Developing the project charter 
B. Developing the preliminary project scope statement 
C. Developing the project managemen...
Voorbeeld 1 van de 3 pagina's
In winkelwagenITPM Chapter 4 Exam 2 Questions And 
Answers 100% Verified 2024 
Which process involves working with stakeholders to create the document that formally 
authorizes a project? 
A. Developing the project charter 
B. Developing the preliminary project scope statement 
C. Developing the project managemen...
ITPM Exam 2 Review Questions And 
Answers 100% Verified 2024 
Establishing the project scope and identifying risks are activities of ________ agile phase - 
answerInception 
In which agile phase the Beta testing is performed? - answerTransition 
Which of the following is NOT an agile framework? - an...
Voorbeeld 1 van de 3 pagina's
In winkelwagenITPM Exam 2 Review Questions And 
Answers 100% Verified 2024 
Establishing the project scope and identifying risks are activities of ________ agile phase - 
answerInception 
In which agile phase the Beta testing is performed? - answerTransition 
Which of the following is NOT an agile framework? - an...
ITPM - Exam 3 Kahoot Questions And 
Answers 100% Verified 2024 
agile - answerIn which methodology, testing is performed concurrently along with 
development? 
a. waterfall 
b. prototype 
c. agile 
d. all of the above 
true - answerT/F: in agile, scrum and XP framework don't put emphasis on documen...
Voorbeeld 1 van de 3 pagina's
In winkelwagenITPM - Exam 3 Kahoot Questions And 
Answers 100% Verified 2024 
agile - answerIn which methodology, testing is performed concurrently along with 
development? 
a. waterfall 
b. prototype 
c. agile 
d. all of the above 
true - answerT/F: in agile, scrum and XP framework don't put emphasis on documen...
ITPM Exam 2 Study Guide With Complete 
Solutions 
Three pervasive problems with IT projects - answerLate delivery, over budget, failure to 
meet business requirements 
IT Portfolio Management (ITPM) - answerManaging IT assets to improve portfolio 
performance 
Risks associated with an IT project - a...
Voorbeeld 1 van de 1 pagina's
In winkelwagenITPM Exam 2 Study Guide With Complete 
Solutions 
Three pervasive problems with IT projects - answerLate delivery, over budget, failure to 
meet business requirements 
IT Portfolio Management (ITPM) - answerManaging IT assets to improve portfolio 
performance 
Risks associated with an IT project - a...
ITPM Exam 1 Questions And Answers 100% 
Solved 2024/2025 
A difference between operations and projects is that operations end when their 
objectives have been reached, whereas projects do not. 
a) true 
b) false 
FALSE 
During the planning phase of a project, the project manager and team identify 
v...
Voorbeeld 2 van de 8 pagina's
In winkelwagenITPM Exam 1 Questions And Answers 100% 
Solved 2024/2025 
A difference between operations and projects is that operations end when their 
objectives have been reached, whereas projects do not. 
a) true 
b) false 
FALSE 
During the planning phase of a project, the project manager and team identify 
v...
ITPM Final Exam Questions And Answers 
1005 Solved 2024/2025 
______ of a Project Manager's job is communication. - answer95% 
What are the types of communication? - answerInternal, external, formal, informal, vertical, 
horizontal, official, unofficial, written, oral, verbal, and non-verbal 
Inter...
Voorbeeld 2 van de 12 pagina's
In winkelwagenITPM Final Exam Questions And Answers 
1005 Solved 2024/2025 
______ of a Project Manager's job is communication. - answer95% 
What are the types of communication? - answerInternal, external, formal, informal, vertical, 
horizontal, official, unofficial, written, oral, verbal, and non-verbal 
Inter...
ITPM Exam Questions And Answers 1005 
Solved 2024/2025 
What is a business case, at which stage is it done, what elements does it include? - 
answerThe justification for doing the project 
What are the stages of Schedule development? - answerActivities from WBS 
Estimate durations 
Work out dependen...
Voorbeeld 2 van de 15 pagina's
In winkelwagenITPM Exam Questions And Answers 1005 
Solved 2024/2025 
What is a business case, at which stage is it done, what elements does it include? - 
answerThe justification for doing the project 
What are the stages of Schedule development? - answerActivities from WBS 
Estimate durations 
Work out dependen...
ITPM HF-Fragen Exam Questions And 
Answers 100% Verified 2024 
Figure out the impact on the scope of the work and the cost before you write up the change 
request - answerA team member approaches you with a change that could cut your schedule 
down by a month. What is the first thing you should do? ...
Voorbeeld 4 van de 107 pagina's
In winkelwagenITPM HF-Fragen Exam Questions And 
Answers 100% Verified 2024 
Figure out the impact on the scope of the work and the cost before you write up the change 
request - answerA team member approaches you with a change that could cut your schedule 
down by a month. What is the first thing you should do? ...
ITPM Final Exam Questions And Answers 
100% Verified 2024 
What are the attributes of a project? - answerTime frame 
Purpose 
Ownership 
Resources 
Roles 
Risks / Assumptions 
Interdependent tasks 
Organizational change 
Operating in enviro bigger than project 
Describe the different roles and skill...
Voorbeeld 3 van de 24 pagina's
In winkelwagenITPM Final Exam Questions And Answers 
100% Verified 2024 
What are the attributes of a project? - answerTime frame 
Purpose 
Ownership 
Resources 
Roles 
Risks / Assumptions 
Interdependent tasks 
Organizational change 
Operating in enviro bigger than project 
Describe the different roles and skill...
ITPM Quiz 5 Exam Questions And Answers 
100% Verified 
During executing, the project manager determines that a change is needed to material purchased 
for the project. The project manager calls a meeting of the team to plan how to make the change. 
This is an example of: 
Answers: 
Management by obj...
Voorbeeld 2 van de 13 pagina's
In winkelwagenITPM Quiz 5 Exam Questions And Answers 
100% Verified 
During executing, the project manager determines that a change is needed to material purchased 
for the project. The project manager calls a meeting of the team to plan how to make the change. 
This is an example of: 
Answers: 
Management by obj...
ITPM Exam Questions And Answers 100% 
Verified 
scope, time, cost - answerWhat factors have the biggest impact on IT projects? 
1) high turnover rates of IT workers 
2) level of uniqueness and complexity 
3) difficulty in getting accurate customer requirements 
4) rate of change in requirements 
5) ...
Voorbeeld 2 van de 7 pagina's
In winkelwagenITPM Exam Questions And Answers 100% 
Verified 
scope, time, cost - answerWhat factors have the biggest impact on IT projects? 
1) high turnover rates of IT workers 
2) level of uniqueness and complexity 
3) difficulty in getting accurate customer requirements 
4) rate of change in requirements 
5) ...
ITPM - Integration Management Exam 
Questions And Answers 100% Verified 
2024/2025 
1. Which of the following is NOT a Project Constraint? 
A. Quality 
B. Scale 
C. Time 
D. Cost - answerScale (Time, Cost, Scope, Resources, Quality, Risk) 
2. A project manager is running a data center installation p...
Voorbeeld 2 van de 5 pagina's
In winkelwagenITPM - Integration Management Exam 
Questions And Answers 100% Verified 
2024/2025 
1. Which of the following is NOT a Project Constraint? 
A. Quality 
B. Scale 
C. Time 
D. Cost - answerScale (Time, Cost, Scope, Resources, Quality, Risk) 
2. A project manager is running a data center installation p...
ITPM - Cost Management Exam Questions 
And Answers 100% Verified 2024/2025 
BAC 
Budget at completion 
- No formula—it's the project budget 
- How much money you'll spend on the project 
PV 
Planned value 
- BAC * Planned % complete 
- What your schedule says you should have spent (planned) 
EV ...
Voorbeeld 2 van de 12 pagina's
In winkelwagenITPM - Cost Management Exam Questions 
And Answers 100% Verified 2024/2025 
BAC 
Budget at completion 
- No formula—it's the project budget 
- How much money you'll spend on the project 
PV 
Planned value 
- BAC * Planned % complete 
- What your schedule says you should have spent (planned) 
EV ...
ITPM Chapter 10 Exam Questions And 
Answers 100% Verified 
T/F: Project members should either have strong technical skills or soft skills. - answerFalse 
T/F: Adding more people to a project that is falling behind schedule often causes more setbacks 
because of the increased complexity of communicat...
Voorbeeld 2 van de 5 pagina's
In winkelwagenITPM Chapter 10 Exam Questions And 
Answers 100% Verified 
T/F: Project members should either have strong technical skills or soft skills. - answerFalse 
T/F: Adding more people to a project that is falling behind schedule often causes more setbacks 
because of the increased complexity of communicat...
ITPM chapter 9 Exam Questions with 100% 
Correct Answers 
T/F: Extrinsic motivation causes people to participate in an activity for their own enjoyment. - 
answerFalse 
T/F: Maslow's hierarchy of needs states that people's behaviors are guided or motivated by a 
sequence of needs. - answerTrue 
T/...
Voorbeeld 2 van de 6 pagina's
In winkelwagenITPM chapter 9 Exam Questions with 100% 
Correct Answers 
T/F: Extrinsic motivation causes people to participate in an activity for their own enjoyment. - 
answerFalse 
T/F: Maslow's hierarchy of needs states that people's behaviors are guided or motivated by a 
sequence of needs. - answerTrue 
T/...
ITPM Exam Questions with 100% Correct 
Answers 
b. 25 percent - answer1. Approximately what percentage of the world's gross domestic 
product is spent on projects? 
a. 10 percent 
b. 25 percent 
c. 50 percent 
d. 75 percent 
c. Lower cost of capital - answer2. Which of the following is not a potent...
Voorbeeld 3 van de 23 pagina's
In winkelwagenITPM Exam Questions with 100% Correct 
Answers 
b. 25 percent - answer1. Approximately what percentage of the world's gross domestic 
product is spent on projects? 
a. 10 percent 
b. 25 percent 
c. 50 percent 
d. 75 percent 
c. Lower cost of capital - answer2. Which of the following is not a potent...
ITPM chapter 8 Exam Questions with 100% 
Correct Answers 
T/F: The quality assurance process involves taking responsibility for quality throughout the 
project's life cycle. - answerTrue 
T/F: Validated changes and validated deliverables are the outputs of the quality assurance 
process. - answerFa...
Voorbeeld 2 van de 5 pagina's
In winkelwagenITPM chapter 8 Exam Questions with 100% 
Correct Answers 
T/F: The quality assurance process involves taking responsibility for quality throughout the 
project's life cycle. - answerTrue 
T/F: Validated changes and validated deliverables are the outputs of the quality assurance 
process. - answerFa...
ITPM chapter 5 Exam Questions with 
100% Correct Answers 
.deliverable - answerThe term ______ describes a product produced as part of a project. 
the work involved in creating the products and the processes used to create them. - 
answerScope refers to: 
Collecting requirements - answer_____ involv...
Voorbeeld 1 van de 2 pagina's
In winkelwagenITPM chapter 5 Exam Questions with 
100% Correct Answers 
.deliverable - answerThe term ______ describes a product produced as part of a project. 
the work involved in creating the products and the processes used to create them. - 
answerScope refers to: 
Collecting requirements - answer_____ involv...
Studenten hebben al meer dan 850.000 samenvattingen beoordeeld. Zo weet jij zeker dat je de beste keuze maakt!
Geen gedoe — betaal gewoon eenmalig met iDeal, creditcard of je Stuvia-tegoed en je bent klaar. Geen abonnement nodig.
Studenten maken samenvattingen voor studenten. Dat betekent: actuele inhoud waar jij écht wat aan hebt. Geen overbodige details!
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper Fyndlay. Stuvia faciliteert de betaling aan de verkoper.
Nee, je koopt alleen deze samenvatting voor $45.49. Je zit daarna nergens aan vast.
4,6 sterren op Google & Trustpilot (+1000 reviews)
Afgelopen 30 dagen zijn er 64670 samenvattingen verkocht
Opgericht in 2010, al 15 jaar dé plek om samenvattingen te kopen