ITPM - Integration Management Exam Questions And Answers Verified|Update 2024/2025
1 ansicht 0 mal verkauft
Kurs
ITPM
Hochschule
ITPM
ITPM - Integration Management Exam Questions And Answers Verified|Update 2024/2025
1. Which of the following is NOT a Project Constraint?
A. Quality
B. Scale
C. Time
D. Cost
Scale (Time, Cost, Scope, Resources, Quality, Risk)
2. A project manager is running a data center installation pro...
ITPM - Integration Management Exam
Questions And Answers Verified|Update
2024/2025
1. Which of the following is NOT a Project Constraint?
A. Quality
B. Scale
C. Time
D. Cost
Scale (Time, Cost, Scope, Resources, Quality, Risk)
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he's run over his budget because the staff turned out to be more expensive than
planned. The stakeholder's unhappy that when the project is over, the servers won't have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
A. Quality
B. Resource
C. Time
D. Cost
Time
3. Which of the following is NOT an example of operational work? (Prozesse)
A. Building a purchase order system for accounts payable
B. Submitting weekly purchase orders through a purchase order system
C. Deploying weekly anti-virus software updates
D. Yearly staff performance evaluations
Building a purchase order system for accounts payable
4. You're managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is the
BEST way to handle this situation?
A. Refuse to work with him because he's being difficult
B. Appeal to the accountant's manager and ask to have him required to take training
C. Get a special dispensation so that the accountant doesn't have to go to the training
D. Work with him to understand his concerns and do what you can to help alleviate them without
compromising your project
Work with him to understand his concerns and do what you can to help alleviate them without
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
A. Resource List
B. Stakeholder Register
C. Enterprise Environmental Factors
D. Project Plan
Stakeholder Register
6. Your manager asks you where to find a list of projects that should be managed together. What is
the
BEST place to find this information?
A. Project Plan
B. Project Charter
Alle Vorteile der Zusammenfassungen von Stuvia auf einen Blick:
Garantiert gute Qualität durch Reviews
Stuvia Verkäufer haben mehr als 700.000 Zusammenfassungen beurteilt. Deshalb weißt du dass du das beste Dokument kaufst.
Schnell und einfach kaufen
Man bezahlt schnell und einfach mit iDeal, Kreditkarte oder Stuvia-Kredit für die Zusammenfassungen. Man braucht keine Mitgliedschaft.
Konzentration auf den Kern der Sache
Deine Mitstudenten schreiben die Zusammenfassungen. Deshalb enthalten die Zusammenfassungen immer aktuelle, zuverlässige und up-to-date Informationen. Damit kommst du schnell zum Kern der Sache.
Häufig gestellte Fragen
Was bekomme ich, wenn ich dieses Dokument kaufe?
Du erhältst eine PDF-Datei, die sofort nach dem Kauf verfügbar ist. Das gekaufte Dokument ist jederzeit, überall und unbegrenzt über dein Profil zugänglich.
Zufriedenheitsgarantie: Wie funktioniert das?
Unsere Zufriedenheitsgarantie sorgt dafür, dass du immer eine Lernunterlage findest, die zu dir passt. Du füllst ein Formular aus und unser Kundendienstteam kümmert sich um den Rest.
Wem kaufe ich diese Zusammenfassung ab?
Stuvia ist ein Marktplatz, du kaufst dieses Dokument also nicht von uns, sondern vom Verkäufer EXAMSMART. Stuvia erleichtert die Zahlung an den Verkäufer.
Werde ich an ein Abonnement gebunden sein?
Nein, du kaufst diese Zusammenfassung nur für 9,48 €. Du bist nach deinem Kauf an nichts gebunden.