100% Zufriedenheitsgarantie Sofort verfügbar nach Zahlung Sowohl online als auch als PDF Du bist an nichts gebunden
logo-home
PRM3701 ASSIGNMENT 4 SEMESTER 2 2024 The project life cycle sequentially passes through four stages. The starting point begins the moment the project is given a go ahead. Match the stages below according to their correct explanation. In practice the t 2,69 €   In den Einkaufswagen

Prüfung

PRM3701 ASSIGNMENT 4 SEMESTER 2 2024 The project life cycle sequentially passes through four stages. The starting point begins the moment the project is given a go ahead. Match the stages below according to their correct explanation. In practice the t

 29 mal angesehen  3 mal verkauft
  • Kurs
  • Hochschule

PRM3701 ASSIGNMENT 4 SEMESTER 2 2024 The project life cycle sequentially passes through four stages. The starting point begins the moment the project is given a go ahead. Match the stages below according to their correct explanation. In practice the terms of a project and program cause conf...

[ Mehr anzeigen ]

vorschau 4 aus 74   Seiten

  • 5. september 2024
  • 74
  • 2024/2025
  • Prüfung
  • Unbekannt
avatar-seller
BMZ ACADEMY




BMZ ACADEMY




@061 262 1185/068 053 8213



BMZ ACADEMY 061 262 1185/068 053 8213

,9/5/24, 10:53 AM Assessment 4




PRM3701-24-S2  Welcome Message  Assessment 4

QUIZ




Question 1

Not yet answered

Marked out of 1.00




The project life cycle sequentially passes through four stages. The starting point begins the moment the project is given a go
ahead. Match the stages below according to their correct explanation.


Defining Major responsibilities are assigned

Planning What will the budget be

Executing The physical product is produced

Closing Post-project review




Question 2

Not yet answered

Marked out of 1.00




In practice the terms of a project and program cause confusion. Which of the following is a good example of a program?


a. Planting a garden

b. Developing a new residential area that includes six custom homes

c. Developing a new marketing plan

d. Taking notes each class meeting to prepare for the final

e. Planning a wedding

Clear my choice




https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=21867331&cmid=941682 1/11

,9/5/24, 10:53 AM Assessment 4

Question 3

Not yet answered

Marked out of 1.00




Which dimension of project management centers on creating a temporary social system within a larger organizational
environment that combines the talents of a divergent set of professionals working to complete the project?



Select one:
a. Communication

b. Sociocultural

c. Social

d. Technical

e. Scheduling

Clear my choice




Question 4
Not yet answered

Marked out of 1.00




In project life cycle stages, the design team might plan a major commitment of resources in the defining stage, while the
quality team would expect their major effort to increase in the latter stages of the project life cycle. As the number of small
projects increase within an organization's portfolio, what is a challenge an organization faces?


a. Sharing resources

b. Measuring efficiency

c. Managing risk

d. Prioritizing projects

e. All of these are challenges

Clear my choice




https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=21867331&cmid=941682 2/11

, 9/5/24, 10:53 AM Assessment 4

Question 5

Not yet answered

Marked out of 1.00




A list of potential projects, several criteria, weights for those criteria, and criteria scores for those projects are all typically
included on a ___________ matrix.


a. Multiple criteria

b. Project screening

c. Project selection

d. Project elimination

e. Project assessment

Clear my choice




Question 6
Not yet answered

Marked out of 1.00




Jack’s organization has many projects ongoing concurrently. He finds himself starting and stopping work on one task to go
and work on another task, and then return to the work on the original task. Jack is experiencing


a. poor scheduling

b. excess work burden.

c. flexible tasking.

d. multitasking.

e. burnout.

Clear my choice




Question 7
Not yet answered

Marked out of 1.00




The following are responsibilities of the governance team when managing a portfolio system are listed below. Identify which
option below is not a responsibility


a. deciding how organizational resources are allocated among the different types of projects

b. publishing the priority of every project and ensuring the process is open and free of power politics.

c. evaluating the progress of the projects in the portfolio.

d. constant scanning of the external environment to determine if organizational selection criteria need to be changed.

e. communicating which projects are approved.

Clear my choice



https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=21867331&cmid=941682 3/11

Alle Vorteile der Zusammenfassungen von Stuvia auf einen Blick:

Garantiert gute Qualität durch Reviews

Garantiert gute Qualität durch Reviews

Stuvia Verkäufer haben mehr als 700.000 Zusammenfassungen beurteilt. Deshalb weißt du dass du das beste Dokument kaufst.

Schnell und einfach kaufen

Schnell und einfach kaufen

Man bezahlt schnell und einfach mit iDeal, Kreditkarte oder Stuvia-Kredit für die Zusammenfassungen. Man braucht keine Mitgliedschaft.

Konzentration auf den Kern der Sache

Konzentration auf den Kern der Sache

Deine Mitstudenten schreiben die Zusammenfassungen. Deshalb enthalten die Zusammenfassungen immer aktuelle, zuverlässige und up-to-date Informationen. Damit kommst du schnell zum Kern der Sache.

Häufig gestellte Fragen

Was bekomme ich, wenn ich dieses Dokument kaufe?

Du erhältst eine PDF-Datei, die sofort nach dem Kauf verfügbar ist. Das gekaufte Dokument ist jederzeit, überall und unbegrenzt über dein Profil zugänglich.

Zufriedenheitsgarantie: Wie funktioniert das?

Unsere Zufriedenheitsgarantie sorgt dafür, dass du immer eine Lernunterlage findest, die zu dir passt. Du füllst ein Formular aus und unser Kundendienstteam kümmert sich um den Rest.

Wem kaufe ich diese Zusammenfassung ab?

Stuvia ist ein Marktplatz, du kaufst dieses Dokument also nicht von uns, sondern vom Verkäufer BMZAcademy. Stuvia erleichtert die Zahlung an den Verkäufer.

Werde ich an ein Abonnement gebunden sein?

Nein, du kaufst diese Zusammenfassung nur für 2,69 €. Du bist nach deinem Kauf an nichts gebunden.

Kann man Stuvia trauen?

4.6 Sterne auf Google & Trustpilot (+1000 reviews)

45.681 Zusammenfassungen wurden in den letzten 30 Tagen verkauft

Gegründet 2010, seit 14 Jahren die erste Adresse für Zusammenfassungen

Starte mit dem Verkauf
2,69 €  3x  verkauft
  • (0)
  Kaufen