BUS 375-2020-Final Exam Part 1. BUS 375
Which of the following schedule compression techniques is often the lowest risk and with the added benefit of lowering the cost? Answer Selected Answer: Descoping Correct Answer: Descoping Question 2 4 out of 4 pointsIf the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and the most likely time is 12 weeks, then the expected duration is: Answer Selected Answer: 13 weeks Correct Answer: 13 weeks Question 3 4 out of 4 pointsAn activity in a network has the following characteristics: ES = 5, EF = 9 and LF = 12. LS = _____. Answer Selected Answer: 8 Correct Answer: 8 Question 4 4 out of 4 pointsWhich of the following network diagramming methods do not use dummy activities? Answer Selected Answer: PDM Correct Answer: PDM Question 5 4 out of 4 points Smoothing out project resources from period to period is called Answer Selected Answer: Resource leveling Correct Answer: Resource leveling Question 6 4 out of 4 pointsIf the slack in a 12 week activity is 6 weeks and ES = 4, then LF = _____. Answer Selected Answer: 22 Correct Answer: 22 Question 7 4 out of 4 points In which of the following schedule compression techniques is the cost of rework usually the greatest? Answer Selected Answer: Performing series work in parallel Correct Answer: Performing series work in parallel Question 8 4 out of 4 points Which type of chart provides the least
Written for
Document information
- Uploaded on
- June 4, 2021
- Number of pages
- 20
- Written in
- 2020/2021
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
which of the following schedule compression techniques is often the lowest risk and with the added benefit of lowering the cost answer selected answer descoping correct answer descoping question 2