1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results,
whereas the functional manager is responsible for providing the resources needed to achieve the results.
(Points: 5)
mixed-mode
matrix
autonomous project
functional
2. (TCO H) What is ...
1. (TCO A) In the _____ organization structure, the project manager is responsible for the project results,
whereas the functional manager is responsible for providing the resources needed to achieve the results.
(Points : 5)
mixed-mode
matrix
autonomous project
functional
2. (TCO H) What is the longest phase of the project life cycle? (Points : 5)
Initiating
Planning
Performing
Closing
3. (TCO B) The lowest level item of any one branch of the WBS is called a(n) _____. (Points : 5)
object item
task statement
work package
activity node
4. (TCO D) A _____ is a predefined set of actions that will be implemented if the risk event occurs. (Points
: 5)
management proposal
classification array
contingency plan
risk contingency matrix
5. (TCO F) _____ the project involves measuring actual progress and comparing it to planned progress.
(Points : 5)
Planning
, Scheduling
Forecasting
Controlling
6. (TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a
particular path can be delayed without jeopardizing the completion of the project by its required
completion time. (Points : 5)
total time
free time
total slack
cumulative slack
7. (TCO G) Which of the following is not an advantage of using project management software? (Points :
5)
Accuracy
The learning curve
Speed
Record keeping
8. (TCO A) Which of the following is not an example of a project? (Points : 5)
Starting up a restaurant
Creating a website for a company
Raising money for a disaster-relief trip
Emptying the recycling everyday
9. (TCO C) Why are activities drawn in a serial relationship on a network diagram? (Points : 5)
The activities use different resources.
The activities are independent of each other.
From a technical standpoint, the activities must be performed in that sequence.
The order of completion doesn’t matter.
10. (TCO F) The project cost estimate is allocated to _____. (Points : 5)
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller boomamor2. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.49. You're not tied to anything after your purchase.