ACQ202 Test 5
1) As production of an item increases, what impact does that typically have on
the unit cost? [Recognize the impact of manufacturing on cost, schedule and performance.]
Unit cost
decreases
Unit cost decreases initially, then
increases
Unit cost
increases
No
impact
2) Design changes that are made after the beginning of production tend to
be equal in cost to changes made prior to production. [Identify how instability of
requirements, design, and production processes impact program cost and schedule.]
Fals
e
True
3) In determining the correct appropriation for funding the development of a
product improvement, the first/primary consideration is: [10c. Identify the proper
DoD Appropriation Category to be used for each of the phases of a Product Improvement Program.]
Will it increase the performance
capability?
Will the same contractor produce the
item?
Will the operator install the
modification?
Is the system still in
production?
4) Which of the following are duties of a Program Integrator (Select all that
apply)? [17a. Identify the relationship between the Program Management Office, the Procuring
Contracting Officer, Administrative Contracting Officer, and Program Integrator.]
Provide data to the Program
Manager
This study source was downloaded by 100000832558064 from CourseHero.com on 03-04-2022 20:24:29 GMT -06:00
team
Has a direct line of communication with the Procuring
Contracting Officer
Administering day to day contractual activities after
contract award
5) When a contractor begins work generated by a change order that does not
have a full negotiated agreement on terms of work, cost, and schedule signed
by both parties, a contract change has been initiated that is . [17b.
Contrast a Change Order with a Supplemental Agreement.]
Undefinitize
d
Constructiv
e
Unconstructi
ve
Definitize
d
6) Personal liability for unauthorized commitments is determined by
. [17c. Identify the causes and consequences of constructive changes and
unauthorized commitments.]
The procedures of each
agency
The Government Program
Manager
The Administrative Contracting
Officer
The Program Management
Office
7) Statistical process control is one way of measuring by charting
random and unique events in the manufacturing process. [37c. Identify methods
of controlling manufacturing costs (e.g., process proofing, variability reduction, and statistical process
This study source was downloaded by 100000832558064 from CourseHero.com on 03-04-2022 20:24:29 GMT -06:00
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller newsolutions. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $17.39. You're not tied to anything after your purchase.