100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ACQ 202 / ACQ202 Module 4 Exam, Part I $17.00   Add to cart

Exam (elaborations)

ACQ 202 / ACQ202 Module 4 Exam, Part I

 1 view  0 purchase
  • Course
  • Institution

Module 4 Exam, Part I Back to Status page contains 19 Questions 1) A Government official who obligates the Government on a contract without having sufficient funds to cover that expense has violated the _______________. [Select the appropriate public law (i.e., Misappropriation Act, Anti-Defic...

[Show more]

Preview 4 out of 52  pages

  • April 26, 2022
  • 52
  • 2021/2022
  • Exam (elaborations)
  • Questions & answers
avatar-seller
Module 4 Exam, Part I
Back to Status page
contains 19 Questions

1) A Government official who obligates the Government on a contract without having
sufficient funds to cover that expense has violated the _______________. [Select the
appropriate public law (i.e., Misappropriation Act, Anti-Deficiency Act, Bona Fide Need)
that applies to the use of appropriated funds under specific circumstances.]
Anti-Deficiency Act

Misappropriation Act

Bona Fide Need Rule

Reprogramming Thresholds



2) The Army can transfer excess funds from a Procurement appropriation to a Research,
Development, Test, and Evaluation (RDT&E) appropriation to cover a funding shortfall of
$3 million without prior approval of Congress. [Given a funding shortfall, apply the rules
governing reprogramming of appropriated funds in each appropriation category to resolve
the problem.]
True

False


3) Select the best statement about the use of Technical Reviews in the current acquisition
environment. [Relate the different types of program unique specifications to their
appropriate configuration baselines and technical review requirements.]
Technical Reviews should be tailored to assess development maturity and risk and to

determine readiness to proceed to the next phase.
Technical Reviews waste valuable Government and contractor time and should be

eliminated to allow more focus on program execution.
The same standard set of Technical Reviews should always be conducted on every

program to ensure the PM has complete data to support decisions.
Technical Reviews are essential since they are vehicles for program problem solving

and training new people on the details of the program.

,4) What are some of the planning challenges that must be considered when taking
commercial items and modifying them for military use (Select all that apply)? [Identify the
impact on configuration management when commercial items are used in the system.]
Management of government furnished equipment

Maintain technical data

Integration

Availability of test ranges and personnel

Long-term logistics support


5) An Operational Assessment will provide operational effectiveness and suitability data.
[Identify the role of Early Operational Assessment (EOA) and Operational Assessment
(OA) in reducing program risk.]
True

False


6) A program manager should normally look for opportunities to integrate developmental
testing (DT) and operational testing (OT) in order to save time and money. [Identify the
risks and benefits associated with integrated Developmental Testing/Operational Testing
(DT/OT).]
False

True


7) A program deviation occurs if the PM thinks his/her program will not meet the threshold
value established for a performance parameter in the Acquisition Program Baseline.
[Identify when program deviations occur and the actions that should be taken by the
Program Manager.]
False

True


8) Where would the initial Functional Baseline be reviewed to ensure that it covers all the
Government's capability needs? [Identify the purpose of specific technical reviews and

,their relationship to the acquisition process.] [Remediation Accessed :N]
Systems Functional Review

Critical Design Review

Preliminary Design Review

Test Readiness Review


9) What group is used to help control the configuration of external interfaces for a system?
[Identify the roles, responsibilities, and methods for interface control and technical data
management.]
Interface Control Working Group

Overarching Integrated Product Team

Integrated Logistics Support Management Team

Joint Test and Evaluation Planning Group


10) Which of the following configuration baselines is used to define design requirements for
each of the components or configuration items of a system? [Identify the relationship
between configuration baselines, specifications, and configuration management planning.]
[Remediation Accessed :N]
Allocated Baseline

Functional Baseline

Product Baseline

Maintenance Baseline


11) The Program Manager just received approval of his proposed acquisition strategy with
one exception: he has been directed to make maximum use of existing Air Force software.
Which of the best software acquisition practices is most applicable to his situation?
[Identify developer practices essential for creation of high quality software.]
Assess reuse risks and cost

Inspect requirements and design

, Use metrics to manage

Use system based software design


12) A program deviation (informally known as a "breach") from the Acquisition Program
Baseline (APB) occurs when the Program Manager (PM) has reason to believe that the
current estimate of a performance, schedule, or cost parameter is not within the threshold
value for that parameter. When a deviation occurs, the PM will notify the Milestone
Decision Authority (MDA) ________________ that a program deviation has occurred.
[Relate the Acquisition Program Baseline (APB) to planning, control, and risk
management in attaining cost, schedule and performance goals.]
Immediately

Within 30 days

Within 60 days

Within 90 days


13) Instability of user capability needs, design, and production processes are most likely to
cause _________________. [Identify how instability of user capability needs, design, and
production processes impact program cost and schedule.]
Cost increases and schedule slips

Cost decreases and schedule slips

Cost decreases without impacting schedule

Schedule slips without impacting cost


14) Which technical review is held during the Engineering and Manufacturing Development
Phase to assess the final design after the "build to" baseline has been achieved? [Trace the
maturation of system design information as it evolves through the acquisition life cycle of a
system.]
Critical Design Review (CDR)

Preliminary Design Review (PDR)

System Requirements Review (SRR)

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Marilyn77. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $17.00. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

72799 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$17.00
  • (0)
  Add to cart