European Business School, London (EBS London)
BBA
Project Management 2nd Edition by Pinto
All documents for this subject (14)
Seller
Follow
smith2324
Reviews received
Content preview
Project Management, 2e (Pinto)
Chapter 10 Project Scheduling: Lagging, Crashing, and Activity Networks
10.1 True/False
1) Finish to start lags are the same as additional activity slack.
Answer: FALSE
Diff: 2
Section: 10.1 Lags in Precedence Relationships
Skill: Factual
AACSB Tag: Reflective
2) The least common type of lag relationship occurs when a successor's finish is dependent upon
a predecessor's start.
Answer: TRUE
Diff: 2
Section: 10.1 Lags in Precedence Relationships
Skill: Factual
AACSB Tag: Reflective
4) In order to accelerate completion of a project, the manager must crash critical path activities.
Answer: TRUE
Diff: 1
Section: 10.3 Crashing Projects
Skill: Factual
AACSB Tag: Reflective
5) The critical path may not contain a dummy activity.
Answer: FALSE
Diff: 1
Section: 10.3 Crashing Projects
Skill: Factual
AACSB Tag: Reflective
, 6) Quite often the marginal gains in employee productivity decrease dramatically with the
increased use of overtime.
Answer: TRUE
Diff: 2
Section: 10.3 Crashing Projects
Skill: Factual
AACSB Tag: Reflective
8) AOA is a more useful technique than AON if the project is complex and has many significant
milestones.
Answer: TRUE
Diff: 2
Section: 10.4 Activity-on-Arrow Networks
Skill: Factual
AACSB Tag: Reflective
9) Networks are adaptable and useful for all scheduling challenges that an organization faces.
Answer: FALSE
Diff: 2
Section: 10.5 Controversies in the Use of Networks
Skill: Factual
AACSB Tag: Reflective
10) Most activity estimations using PERT methods lead to overly optimistic activity duration
estimates.
Answer: TRUE
Diff: 2
Section: 10.5 Controversies in the Use of Networks
Skill: Factual
AACSB Tag: Reflective
10.2 Fill in the Blank
1) The logical relationship between the start and finish of one activity and the start and finish of
another activity is the __________.
Answer: lag
Diff: 1
Section: 10.1 Lags in Precedence Relationships
Skill: Definition
AACSB Tag: Reflective
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller smith2324. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $3.77. You're not tied to anything after your purchase.