Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe. $17.99   In winkelwagen

Tentamen (uitwerkingen)

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.

 20 keer bekeken  1 keer verkocht

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe.Test Bank For Information Technology Project...

[Meer zien]

Voorbeeld 4 van de 321  pagina's

  • 16 september 2023
  • 321
  • 2023/2024
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
Alle documenten voor dit vak (4)
avatar-seller
DICKSONtheNURSE
Test Bank For Information Technology
Project Management, 9th Edition,
Kathy Schwalbe:2023-2024 WITH
VERIFIED QAS: GRADED A

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE
Chapter 1: Introduction to Project Management


TRUE/FALSE

1. Until the 1980s, project management primarily focused on providing schedule and resource data to top
management in the military, computer, and construction industries.

ANS: T
Until the 1980s, project management primarily focused on providing schedule and resource data to top
management in the military, computer, and construction industries. Today’s project management
involves much more, and people in every industry and every country manage projects.

PTS: 1 DIF: Difficulty: Easy REF: p.2
OBJ: LO: 1-1 NAT: BUSPROG: Technology TOP: Introduction
KEY: Bloom's: Knowledge

2. A difference between operations and projects is that operations end when their objectives have been
reached, whereas projects do not.

ANS: F
Projects are different from operations in that they end when their objectives have been reached or the
project has been terminated.

PTS: 1 DIF: Difficulty: Moderate REF: p.4
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

3. Every project should have a well-defined objective.

ANS: T
A project has a unique purpose. Every project should have a well-defined objective.

PTS: 1 DIF: Difficulty: Easy REF: p.6
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge

4. Projects should be developed in increments.

ANS: T
A project is developed using progressive elaboration. Projects are often defined broadly when they
begin, and as time passes, the specific details of the project become clearer. Therefore, projects should
be developed in increments.

PTS: 1 DIF: Difficulty: Moderate REF: p.6
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE
5. Resources in a project should be used effectively because they are limited.

ANS: T
A project requires resources, often from various areas. Resources, however, are limited and must be
used effectively to meet project and other corporate goals.

PTS: 1 DIF: Difficulty: Moderate REF: p. 7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

6. A project manager’s primary role is to provide the funding for a project.

ANS: F
A project sponsor usually provides the direction and funding for a project.

PTS: 1 DIF: Difficulty: Easy REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge

7. One of the main reasons why project management is challenging is because of the factor of uncertainty.

ANS: T
A project involves uncertainty. Every project is unique and thus it is sometimes difficult to define its
objectives clearly, estimate how long it will take to complete, or determine how much it will cost. This
uncertainty is one of the main reasons project management is so challenging.

PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

8. Questions about how a team will track schedule performance is related to a project’s scope.

ANS: F
Project scope deals with questions such as, “What work will be done as part of the project?”, “What
unique product, service, or result does the customer or sponsor expect from the project?”, or “How will
the scope be verified?”

PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Technology TOP: What is a Project?
KEY: Bloom's: Comprehension

9. In order to be realistic, a project manager should always set discrete goals instead of a range of
objectives.

ANS: F
Projects involve uncertainty and limited resources. Thus they rarely finish according to their original
scope, time, and cost goals. Instead of discrete target goals, it is often more realistic to set a range of
goals.

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE

PTS: 1 DIF: Difficulty: Moderate REF: p.8
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

10. Managing the triple constraint primarily involves making trade-offs between resources and quality.

ANS: F
Managing the triple constraint involves making trade-offs between scope, time, and cost goals for a
project. Experienced project managers know that one must decide which aspect of the triple constraint
is most important.

PTS: 1 DIF: Difficulty: Easy REF: p.9
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Product?
KEY: Bloom's: Knowledge

11. The only responsibility of a project manager is to meet the specific scope, time, and cost goals of a
project.

ANS: F
Project managers must strive not only to meet specific scope, time, cost, and quality goals of projects
but also facilitate the entire process to meet the needs and expectations of people involved in project
activities or affected by them.

PTS: 1 DIF: Difficulty: Moderate REF: p.9
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

12. A project’s stakeholders consist of its customers, users, and suppliers.

ANS: T
Stakeholders are the people involved in or affected by project activities, and include the project sponsor,
project team, support staff, customers, users, suppliers, and even opponents of a project.

PTS: 1 DIF: Difficulty: Moderate REF: p.10
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

13. Opponents of a project do not belong to the category of stakeholders.

ANS: F
Stakeholders are the people involved in or affected by project activities, and include the project sponsor,
project team, support staff, customers, users, suppliers, and even opponents of a project.

PTS: 1 DIF: Difficulty: Moderate REF: p.10
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

Verzekerd van kwaliteit door reviews

Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper DICKSONtheNURSE. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor $17.99. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 72042 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen
$17.99  1x  verkocht
  • (0)
  Kopen