answers 2023 update
OSHA lead construction standard - answer 29CFR1926.62
What is the ten hour PEL - answer 40 mg/m3 (50 x 8 hrs/ hours worked = = 40)
What is the OSHA PEL - answer 50 mg/m3 TWA
What is OSHA Action Level - answer 30 mg/ m3 TWA
Even after the lead-based paint has been weathered, chipped, peeled, or removed from painted
surfaces it can still be available as a potential exposure source through. - answer -soil around
the house and play area
- contaminated dust within the house ( carpet and upholstered furniture)
- contaminated dust on paved areas around the house, on sidewalks, alleys, streets and
parkinglots
HUD requires PHAs and IHAs to inspect what age facilities - answer Pre-1978
In 1970 the U.S? Surgeon General issued a statement title" Medical Aspects of Children Lead
Poisoning, which resulted in Public Law 91-695, the _________________________ in 1971. -
answer Lead-Based Paint Poisoning Prevention Act (LBPPPA)
Lead exposure in construction- Permissible Exposure Limit (PEL) - answer 50 mg/m3
Lead exposure in construction- Action level - answer 30 mg/m3