Project Management In Practice 6th Edition by Jack R. Meredith -Test Bank $26.63   Add to cart

Exam (elaborations)

Project Management In Practice 6th Edition by Jack R. Meredith -Test Bank

 0 view  0 purchase
  • Course
  • Institution

Complete Test Bank (with Questions Answers)

Preview 4 out of 143  pages

  • November 4, 2023
  • 143
  • 2022/2023
  • Exam (elaborations)
  • Questions & answers
avatar-seller
,Chapter 1: The World of Project Management


True/False

1. A primary purpose of forming projects is to assign the responsibility for
accomplishing some organizational task to a specific person or small group.

Answer: True
Response: See section1.1
Level: easy



2. One of the few similarities between project management and general management
is that both exist in the well-defined organizational structure of
superior/subordinates in the overall organization.

Answer: False
Response: See section1.2
Level: medium



3. Many recent developments in project management are being driven by changes in
the nature of the American workforce.

Answer: False
Response: See section1.1
Level: medium



4. There has been a growing use of projects to achieve an organization’s strategic
goals

Answer: True
Response: See section1.1
Level: medium



5. While general managers have their authority limited to specific areas in the
overall organization, project managers have authority over any activity required
by the project.

, Answer: False
Response: See section1.2
Level: medium



6. Projects are always carried out under conditions of uncertainty.

Answer: True
Response: See section1.3
Level: easy



7. One can trade-off time and cost when managing a project, but the project’s
technical specifications must be maintained exactly as the client initially specifies.

Answer: False
Response: See section1.3
Level: medium



8. Nonnumeric project selection methods are only suitable if numeric methods are
not available.

Answer: False
Response: See section1.5
Level: medium


9. When using financial methods for selecting projects, the payback period is the
simplest and best method to use.

Answer: False
Response: See section1.5
Level: medium



10 Rank-ordering a large number of projects can be done with a Q-sort.

Answer: True
Response: See section1.5
Level: medium

, 11. A disadvantage of using the payback period method for selecting projects is that it
cannot reflect the time-value of money.

Answer: True
Response: See section1.5
Level: medium




12. A disadvantage of using the discounted cash flow method (or net present value)
for selecting projects is that it ignores all non-monetary factors associated with the
project except risk.

Answer: True
Response: See section1.5
Level: medium



13. A disadvantage of using scoring models rather than financial models for selecting
projects is that they cannot include the project’s profitability.

Answer: False
Response: See section1.5
Level: medium



14. A PM doesnot need to understand why a project is selected for funding because
he didnot initiate the process.

Answer: False
Response: See section1.5
Level: medium



15. The main distinction between platform and breakthrough projects is that the
former usually depend on existing technology.

Answer: True
Response: See section1.6

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller premiumbiz379. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $26.63. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77254 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$26.63
  • (0)
  Add to cart