100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS AND ANSWERS VERIFIED ANSWERS WITH RATIONALES | UPDATED 2024 | GRADED A | $26.26   Add to cart

Exam (elaborations)

IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS AND ANSWERS VERIFIED ANSWERS WITH RATIONALES | UPDATED 2024 | GRADED A |

 2 views  0 purchase
  • Course
  • Institution

IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS AND ANSWERS VERIFIED ANSWERS WITH RATIONALES | UPDATED 2024 | GRADED A | IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS AND ANSWERS VERIFIED ANSWERS WITH RATIONALES | UPDATED 2024 | GRADED A | IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS AND ANSWERS VE...

[Show more]

Preview 3 out of 23  pages

  • January 5, 2024
  • 23
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
IFMA FMP PROJECT MANAGEMENT EXAM QUESTIONS
AND ANSWERS VERIFIED ANSWERS WITH RATIONALES |
UPDATED 2024 | GRADED A |


If an organization has narrowed the list of contractors submitting proposals but is
still having trouble deciding between them, what could help? - CORRECT
ANSWER The correct answer is: Bidder presentations

Which statement is true of the Execute, Monitor and Control phases of the project
model? - CORRECT ANSWER The correct answer is: These phases are often
concurrently or iteratively performed.

When project managers determine the level of data to collect for monitoring and
controlling project work, what do they not need to verify? - CORRECT
ANSWER The correct answer is: Project work delays due to data collection are
scheduled.

What do project managers submit when they suggest revising the project
management plan to make it feasible given the current situation? - CORRECT
ANSWER The correct answer is: change order.

What is developed to review a final deliverable from an entire system
perspective? - CORRECT ANSWER The correct answer is: Checklist reviews

Which statement is true about the documentation for project closure? -
CORRECT ANSWER The correct answer is: Documentation may include
operations and maintenance manuals.

A project manager wants to minimize risk and provide some independent checks and
balances on contractor work. Which contract model should the organization use? -
CORRECT ANSWER Construction management Your answer is correct.

Construction management is the best choice because it uses an independent
consultant to supervise separate contracts with design firms and construction firms,
which allows for some independent review. (Reference: 3-2-10)

According to the critical path method (CPM) of scheduling, what is the critical
path for any project? - CORRECT ANSWER the longest set of sequential tasks
in the project. Your answer is correct.

The critical path is the longest set of sequential tasks in a project and indicates the

,shortest possible project duration. The critical path is determined using forward
pass scheduling followed by backward pass scheduling.(Reference: 3-2-3)

, Why does a budget need to be closely integrated with the project schedule? -
CORRECT ANSWER costs are allocated to the period in which they occur. Your
answer is correct.

Development of the budget requires close integration with the project schedule
because costs are allocated to the period in which the costs are incurred. Similarly,
budget constraints can require changes to the project schedule such as completing
a task more quickly to minimize financing costs. Budgets are produced after
schedules. Estimates for costs are made during planning rather than waiting until
later.(Reference: 3-2-5)

Which scheduling methods are for activities NOT concurrently performed? -
CORRECT ANSWER Traditional waterfall model scheduling Your answer is
correct.

In forward pass, backward pass, and critical pass scheduling, as many activities
as possible are concurrently performed, constrained by resource availability and
predecessors. The traditional waterfall model does not include these time-saving
processes, and therefore it is rarely used for project scheduling.(Reference: 3-2-3)

Which statement is true about the process steps used to build a project schedule? -
CORRECT ANSWER Failure to agree on a duration estimate may indicate a need
for further task division. Your answer is correct.

Failure to come to agreement on an estimate may indicate the task needs to be
further broken down. Dependencies are part of sequencing. Knowing the skill
levels of personnel affects the length of time required for a task, so determining
this is necessary. Sequencing is not performed during work breakdown structure
creation. (Reference: 3-2-3)

Which statement is true of communications management for an office relocation? -
CORRECT ANSWER Post-relocation orientation brochures can help employees find
their way around.
Your answer is correct.
Which attribute most accurately describes a project? - CORRECT ANSWER The
correct answer is: Projects are finite.

What is an example of how project managers apply sound management
techniques? - CORRECT ANSWER The correct answer is: they break down a
task further if it remains at the same percent completion despite reported progress.

Which is an advantage of using a standardized project management model? -
CORRECT ANSWER The correct answer is: The model is a framework that

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller erickarimi. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $26.26. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81989 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling

Recently viewed by you


$26.26
  • (0)
  Add to cart