You have a requirement for repair parts to support routine maintenance
services at the shop on your base. The parts were
developed using Government funds and are not offered to the general
public. The estimated dollar value of the acquisition is
$275,000.
Which one of the following statements is true? - ANSWER--The use of
simplified acquisition procedures is prohibited.
You are the contracting officer for a firm-fixed-price supply contract
valued at $195,400. Which one of the following
statements about contract closeout is correct? - ANSWER--The contract
is considered closed once you receive evidence of receipt of property
and final payment.
You are the contracting officer for a noncommercial supply contract
valued at $155,600. Which one of the following actions
would be executed using a bilateral modification?
(There is another question almost Identical to this one) - ANSWER--
Making a negotiated equitable adjustment
, CON 2370 SIMPLIFIED ACQUISITION ACTUAL
EXAM QUESTIONS AND CORRECT DETAILED
ANSWERS A GRADE
You have a requirement for a new contract for janitorial services at your
military installation. The Base Commander has
expressed the need for clearly stated performance objectives, as the
current contractor performing the services is not
meeting the Commander's expectations.
Consistent with the order of precedence for requirements documents,
which one of the following documents would be
included in the new contract? - ANSWER--A Performance Work
Statement (PWS)
Which one of the following mandatory Government sources is the first
priority for satisfying a requirement for supplies? - ANSWER--
Inventories of the requiring agency
You are reviewing the requirements package for the purchase of lab
equipment for a health clinic that does not exceed the
SAT. It must be compatible with the equipment currently being used at
the clinic. This is essential in meeting the agency's
needs. Market research identified only one manufacturer able to meet the
requirement for compatible equipment.
Which one of the following is correct regarding the policies for
describing your agency's needs? - ANSWER--The basis for not
providing for maximum competition must be documented in the contract
file
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller erickarimi. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $19.48. You're not tied to anything after your purchase.