What is the name of the code that is the accepted standard for all electrical
wiring in the United States?
- Correct Answer- National Electrical Code
What is the maximum distance between supports of...
What is the name of the code that is the accepted standard for all electrical
wiring in the United States?
- Correct Answer- National Electrical Code
What is the maximum distance between supports of a vertical raceway,
based on NEC Article 620-32?
- Correct Answer- 15 feet
What type of flex would be used to pipe a switch in a wet location?
- Correct Answer- Liquid tight Flex
What is the name for the complete metal system of duct, conduit and flex
that protects the wiring?
- Correct Answer- Raceway
How is the work divided when planning piping and wiring of an elevator
installation?
- Correct Answer- Hoistway, car and machine room
What document may be the only place to look for such information as type
of fixtures, car panel, fire service floor, etc?
- Correct Answer- Job abstract
What information is shown on a pull sheet?
- Correct Answer- Terminal connections
Which type of diagram shows a simplified path from positive to negative for
all components in a circuit?
- Correct Answer- Straight line
, What is shown on the final layout?
- Correct Answer- A plan drawing and an elevation giving dimensions
How are multiple installations of traveling cables numbered for a single
car?
- Correct Answer- From the rail regardless of placement in the hoistway
In the circuit shown, which is the common wired for the second level?
- Correct Answer- DC+
How are wire sizes larger than 4/0 measured?
- Correct Answer- In circular mils
What is the abbreviated term for current carry8ing capacity?
- Correct Answer- Ampacity
What is the minimum size wired for lighting circuits in an elevator
installation?
- Correct Answer- #14
What is the special about wire used for the interlock circuit?
- Correct Answer- It must be rated for 200 degrees C
What is the smallest wire that is permitted in an elevator installation?
- Correct Answer- #24
When bending conduit, what is the maximum number of decrees of bend
allowed between access points?
- Correct Answer- 90 degrees
What is the reference point on the thin-wall bender for the finish line of a
back to back bend?
- Correct Answer- The star point
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller NurseAdvocate. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $7.99. You're not tied to anything after your purchase.