A newly installed 4160V emergency generator has an insulation resistance value of 150 Megohms after one minute with an equipment temperature of 32 degrees C. Is this value acceptable per NETA standards?
No
...
neta ett certified level 3 exams questions with co
Written for
NETA
All documents for this subject (447)
Seller
Follow
NurseAdvocate
Reviews received
Content preview
NETA ETT CERTIFIED LEVEL 3 EXAMS QUESTIONS WITH
COMPLETE SOLUTIONS VERIFIED AND UPDATED
A newly installed 4160V emergency generator has an insulation resistance value
of 150 Megohms after one minute with an equipment temperature of 32 degrees
C. Is this value acceptable per NETA standards?
No
Know the NETA-ATS Insulation Resistance tables
Which test method measures Hydrolyzable Flouride content in SF6 gas?
ASTM D2284
[Standard Test Method for Acidity of Sulfur Hexafluoride]
NETA ATS-2017 Table 100.13
Know the ASTM test names what what they test
The operating speed of a protective relay is dependent on:
* Spring Tension
* Armature core air gap
* Rate of flux built up
,This was originally a 'not question'. This list is not necessarily conclusive. It's simply the
'incorrect' answers to the 'not question'.
According to IEEE C57.106, which test is recommended for routine acceptance of
new, unprocessed oil from a supplier for use in circuit breakers?
ASTM D877
[Standard Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using
Disk Electrodes]
Know IEEE C57 information. Know ASTM tests and definitions
Meter Sockets and meter disconnect switches should generally be connected on
what side of a service disconnecting means?
The line side
This was originally a True/False statement question. The answer stated that the load
side is wrong. The reference above seems to imply that meter sockets and meter
disconnect switches should generally be connected on the line side.
Know NFPA 70
What size neutral resistor would be required to limit the fault current of a 13,800-
480Y/277V 1500kVA Transformer to 5A?
,55.4
Know Ohm's Law. 277 V / 5A = 55.4 ohms
I believe that since this is dealing with the neutral, Line-Neutral voltage (277 V) should
be used in the formula. 5 A on the line will also be 5A on the windings since the
transformer configuration is a Wye configuration. I also believe that the impedance of
the transformer is negligible in this calculation since it isn't mentioned in the question
and presumably would only limit the fault current further.
Correcting the power factor of three-phase loads normally involves adding
(capacitance, inductance) in (series, parallel)
capacitance in parallel
http://archive.is/WOiLd
Typically, power factor is offset by increased inductance. Adding capacitance in parallel
corrects this.
The voltage induced into the armature of a DC motor is known as the:
CEMF
[counter-electromotive force]
https://en.wikipedia.org/wiki/Counter-electromotive_force
As a battery cell starts discharging, internal resistance of the cell will _____ .
increase
, Link leads to a paywall. The reason why the internal resistance increases appears to
have to do with change in electrolyte concentration.
When conducting an ASTM D877 dielectric breakdown test, the fluid is
continuously stirred. True or False
False
Know ASTM tests and definitions. Know IEC tests and definitions.
Some dielectric breakdown tests require stirring, some don't. I guess the point of the
question is to test knowledge of which of these tests involve stirring. It is probably also
useful to know the other differences between the tests. The tests are ASTM D877,
ASTM D1816, and IEC 60156.
What are the necessary requirements to operate two transformers in parallel?
* Same Phase Angle Shift
* Same Polarity
* Same Phase Sequence
* Same Frequency
The original question was a 'not question'. There are other conditions which are nice to
have for optimal operation but are not strictly necessary
What are the convenient (but not necessary) requirements to operate two
transformers in parallel?
* Same voltage ratio and turns ratio
* Same Percentage Impedance
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller NurseAdvocate. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.99. You're not tied to anything after your purchase.