CQM-C Questions and answers latest update
The purpose of Construction Quality Management is to:
Achieve the quality established by properly developed requirements through the combined responsibility, but seperate efforts of contractpr smd government personnel.
Construction Quality Management...
cqm c questions and answers latest update the purp
Written for
Quality Management
All documents for this subject (123)
Seller
Follow
EXAMSMART
Reviews received
Content preview
CQM-C Questions and answers latest update
The purpose of Construction Quality Management is to:
Achieve the quality established by properly developed requirements through the combined
responsibility, but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that construction is
performed.
According to plans and specifications, on time, within a defined budget and a safe work environment.
Partnering relationships are based upon:
Building trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to:
Periodically verify that the contractors system of control is working effectively.
An effective contractor quality control program will:
Be an incentive for work to be done correctly the first time resulting in earlier completion, reduced
field overhead costs, and greater profits.
The success or failure of all contractors is based upon:
The ability to control costs, finance work, estimate jobs, schedule the work, and maintain effective
quality control.
Quality Assurance Personnel have the responsibility to:
Require contractors to maintain the quality specified in the plans and specifications.
Inspection is:
The process by which ongoing and completed work is examined
During the punch-out inspection of a project:
Quality Assurance Personnel must assure that the contractor prepares a punch-list and makes
corrections.
If there is a disagreement whether the contractors work complies with the contract:
The government makes the final determination
Characteristics that describe a definable feature of work include:
Cross-referenced listings to the contractors construction schedule that may have more than one
definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing compliance
with contract requirements.
Follow-up phase
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller EXAMSMART. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.19. You're not tied to anything after your purchase.