List the five steps to a successful tilt-up project. - ANSWER 1. Design 2. Planning 3. Construction 4. Erection 5. Creating Finishes Select three disadvantages of tilt-up construction - ANSWER available space to cast panels weight of panels on certain soils availability of lifting equipment ...