AIC Prep UH Questions and Answers 100% Pass A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour workday, how many days are needed to complete this activity? a. 13 b...