MNO2601 ASSIGNMENT 5 SEMESTER 2 2024 Indicate if the following statement is true or false. Digital information in databases is not seen as inventory. True FalsE A buildings material supplier obtai...
MN02601 Extensive Notes from the prescribed book - Operations Management Notes (1st edition). Alistair Brandon-Jones, Nigel Slack.
UvA BOP complete summary
All for this textbook (25)
Written for
NHL Hogeschool Stenden
International Hotel and Hospitality Management
Operations Management Design
All documents for this subject (1)
Seller
Follow
lisavdf
Reviews received
Content preview
Summary Design Test Operations
Made by Lisa van der Feer in Year 2018-2019
, Critical Path Analysis
EST = Earliest start time
LST = Lastest start time
Float = The maximal time the activity can be delayed without changing the end time
Critical path = Everywhere the float is 0
Then you need something like the table on the left.
Look at the preconditions, if something else has to happen before something.
Then you can fill out these blocks to create the network
Step 1: Start with a start block (node)
Step 2: Put in the activity without preconditions (A, B & C in the example above). Also
add the duration
Step 3: Then put in the next blocks (nodes) behind it’s preconditions. If there are 2
preconditions, like K has in the example, just draw two lines.
Step 4: All ends of the network should end in the finish block.
Now your network looks like this.
Now you have to fill in the nodes (blocks).
Step 5: To find out the EST, add the duration of the previous node to the EST of the
previous node. If there are multiple, take the one that is the highest.
Step 6: To find out the LST, start at the finish. The LST for finish is the same as the EST.
Then simply take the LST of the previous node and subtract the duration of that
node and that is your LST. If there are multiple, take the lowest.
Step 7: The float is the difference between the EST and the LST
Step 8: The Critical Path is where the float is 0.
This is what it should look like
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller lisavdf. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $4.85. You're not tied to anything after your purchase.