The project team is collecting data from system users regarding their needs. Identify the stage of the system life cycle. correct answers Planning and analysis
Identify the task that a healthcare organization should do prior to initiating a search for an information system correct answers Conduc...
HIM 162 Final || All Questions Answered Correctly.
The project team is collecting data from system users regarding their needs. Identify the stage of
the system life cycle. correct answers Planning and analysis
Identify the task that a healthcare organization should do prior to initiating a search for an
information system correct answers Conduct a feasibility study
Identify the true statement about the use of the best of breed strategy correct answers The various
information systems must be interfaced
Identify the component of the request for proposal providers the size of the healthcare
organization and the number of employees who will utilize the information system correct
answers Information for potential vendors
Identify the open ended question correct answers How does the current information system meet
your needs?
The vendor is scheduled to receive 30 percent of their payment when the software is delivered.
This is an example of a _____. correct answers Payment milestone
Three members of the project team are conducting a site visit for an EHR under consideration.
This is an example of a(n) ____. correct answers Evaluation
Identify the tool used to determine what users need in an information system correct answers
Questionnaire
Identify the document that should reviewed to learn about the vendors financial status, the
number of installs of the information system, sample resumes, and more correct answers Request
for proposal
A new graduate asked why the support of the chief executive officer (CEO) for the proposed
EHR was needed. The response should be ____. correct answers Others in the healthcare
organization follow the lead of upper management
The EHR that is currently being selected was initially planned for the inpatients at the hospital.
Now the CIO has instructed the project management team to purchase one that works for both
the inpatient and ambulatory services. This is an example of _____. correct answers Scope creep
Critique this statement: "The HIM director should make the decision on which EHR is
purchased" correct answers The HIM director should be involved in the decision, but so should
other stakeholders
Identify the true statement about a project team correct answers The projects team composition is
based on the needs of the project
, Review the following goal and select the portion of the goal that illustrates the S in the SMART
methodology of goal writing. "Patient revenue will be increased by 20 percent within six
months" correct answers Patient revenue will be increased
The selection committee is at a stalemate on the system to purchase. Identify what should be
done to prevent this from happening? correct answers Develop an objective method of selection
Identify the tangible benefit correct answers The hospital saved $40,000 through the policy
change
Identify a reason for scope creep correct answers Changes to deliverables in the middle of the
project
Identify the project management tool that displays the critical path correct answers PERT chart
Identify the stage in the SDLC where data is collected on the functions required of an
information system correct answers Systems analysis
A system selection tool used to determine the information system to purchase is correct answers
Weighted decision matrix
The contract clause that means "act of God" correct answers Force majeure
The SDLC phase where the healthcare organization will determine whether or not to implement
an information is known as correct answers Project planning
The project managers skills include leadership, organizational skills and correct answers Conflict
management
A project has a specific objection, a set of activities and correct answers Deliverables
The project plans resources components include time, money, staff and correct answers Space
Testing has identified an issue. This issue should be documented in the _____. correct answers
Trouble ticket
Identify the go live strategy is the quickest, but the riskiest, for implementing a new lab system
quickly correct answers Big bang
Identify the question that should be repeated during re-engineering correct answers Why?
In the new information system, the service rendered is stored as a three character alphabetic
field. The old information system stores it as a two digit number. Identify what needs to be done.
correct answers Convert the data
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller FullyFocus. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.99. You're not tied to anything after your purchase.