Which of these documents, might we find in the
Project Manual but they are not contract documents?
(A) The Agreement
(B) Procurement Documents
(C) Addendum
(D) Supplemental Conditions - Correct Answer ✅Answer:
B
Reference: PDPG 11.1.6
Explanation: Procurement requirements are
addressed to prospective bidders or proposers
interested in the project. Although not necessarily
part of a contract, the procurement requirements are
usually bound with other written construction
documents into a project manual.
,CDT Exam Questions and Answers
(Latest Update 2024)
Before a model building code can become the
building code for a jurisdiction, it has to be adopted
by?
(A) Authority Having Jurisdiction
(B) State Government
(C) Building Inspector
(D) International Organization for
Standardization - Correct Answer ✅Answer: A
Reference: PDPG 4.3
Explanation: Before a model building code can
become the building code for a jurisdiction, it has to
be adopted by that AHJ. Once adopted, they then
are responsible for enforcing that building code
within their jurisdiction.
,CDT Exam Questions and Answers
(Latest Update 2024)
The Construction Manager is hired by this entity?
(A) The General contractor
(B) Owner
(C) A/E
(D) Contract Administrator - Correct Answer ✅Answer: B
Reference: PDPG 2.6.4
Explanation: The owner usually engages the
services of a construction manager, an entity that
typically contracts with the owner to provide
construction management services.
The parties to the Construction Agreement are?
(A) General Contractor, Sub Contractor, and
Construction Manager
, CDT Exam Questions and Answers
(Latest Update 2024)
(B) A/E, General Contractor, and Contract
Administrator
(C) Building Official, and General contractor
(D) Owner, Contractor, and A/E - Correct Answer
✅Answer: D
Reference: PDPG 7.2.3.1
Explanation: (PDPG Figure 5.1) The tripartite relationship
among the owner, contractor,
and A/E is created by obligations to third parties to the
contract. For example, the
owner-A/E agreement may require certain duties of the
A/E acting on behalf of the owner
during construction. The contractor has a right to rely on
the proper performance of these
duties. The A/E, similarly, relies on the contractor to
perform certain duties identified in
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Allivia. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.99. You're not tied to anything after your purchase.