One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
T F correct answers True
The Guide to the Project Management Body of Knowledge (PMBOK®) is divided into two main parts, the various business processes that organizations fol...
OMGT Exam 3 || QUESTIONS AND ANSWERS 100%
SOLVED.
One of the primary characteristics of projects as a form of work is the movement of personnel
from project to project.
T F correct answers True
The Guide to the Project Management Body of Knowledge (PMBOK®) is divided into two
main parts, the various business processes that organizations follow in carrying out projects
and the nine knowledge areas applicable to nearly all projects.
T F correct answers True
The earliest finish time of an activity is always later than its latest start time.
T F correct answers False
A project is a one-time undertaking designed to achieve a particular organization goal.
T F correct answers True
There are more resources required during the performance phase of a project than the project
definition phase.
T F correct answers True
A critical path is composed OF activities other than critical activities.
T F correct answers False
Performance or time targets for each major group of activities in a project are set during the
concept phase of a project.
T F correct answers False
Key points in a project, such as when a major activity or phase is completed, are referred to
as lodestones.
T F correct answers False
The earliest start time of an activity is dependent on the earliest start time of its immediate
predecessors.
T F correct answers False
Activities on the critical path may have positive or negative slack as long as the overall slack
time of the critical path is zero.
T F correct answers False
, One characteristic of cloud computing is that the provider's computing resources may serve
multiple consumers with the resources dynamically allocated according to customer demand.
T F correct answers True
Material requirements planning is used to manage dependent demand inventory.
T F correct answers True
MRP does not use backward scheduling.
T F correct answers True
Gross requirements in an MRP record can be met by inventory from previous weeks,
scheduled receipts, or planned receipts.
T F correct answers True
Consider the product structure tree shown below:
Company B has no inventory at any level. They will need 180 Es to make 12 units of end
item X.
T F correct answers True
If a job has a negative critical ratio then it must be early.
T F correct answers False
Distribution requirements planning is used to synchronize supply chain partners at the
production activity control level.
T F correct answers True
All information systems are computer-based.
T F correct answers False
Accuracy is a key performance dimension for strategic decision-making information flows.
T F correct answers False
Since the booked orders figure represents actual customer demand in a master schedule, that
value is always less than or equal to forecasted demand.
T F correct answers False
The order quantity in a periodic review system rises as the on-hand inventory falls.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller ProPerfomer. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.99. You're not tied to anything after your purchase.