Gourmet Pretzels bakes soft pretzels on an assembly line. It currently bakes 800
pretzels each eight-hour shift. If the production is increased to 1,200 pretzels each shift,
then productivity will have increased by: - answer- 50 percent
Consider the following work breakdown structure:
Duration Estimates (Days)
ActivityPrecedesOptimisticMost LikelyPessimisticStartU,V - - - UW 35 50 65 VW,X 28
40 52 WZ 26 35 44 XY 28 40 52 YZ 26 29 38 ZEnd 36 60 84
What is the estimated standard deviation in the time for activity Z? - answer- 8 days
Consider the following work breakdown structure:
Duration Estimates (Days)
ActivityPrecedesOptimisticMost LikelyPessimisticStartU,V - - - UW 35 50 65 VW,X 28
40 52 WZ 26 35 44 XY 28 40 52 YZ 26 29 38 ZEnd 36 60 84
What is the estimated expected (mean) time for project completion? - answer- 170 days
Consider the following work breakdown structure:
Duration Estimates (Days)
ActivityPrecedesOptimisticMost LikelyPessimisticStartU,V - - - UW 35 50 65 VW,X 28
40 52 WZ 26 35 44 XY 28 40 52 YZ 26 29 38 ZEnd 36 60 84
What is the estimated slack time for activity W? - answer- 25 days
Consider the following work breakdown structure:Duration Estimates
(Days)ActivityPrecedesOptimisticMost LikelyPessimisticStartU,V - - - UW 35 50 65
VW,X 28 40 52 WZ 26 35 44 XY 28 40 52 YZ 26 29 38 ZEnd 36 60 84 What is the
probability that the critical path for this project will be completed within 200 days? -
answer- 0.9987
Consider the following work breakdown structure:
Time Estimates (days)
ActivityPrecedesOptimisticMost LikelyPessimisticStartA,B,C - - - AD 38 50 62 BE 90 99
108 CEnd 85 100 115 DF 19 25 31 EEnd 91 100 115 FEnd 62 65 68
What is the estimated slack time for activity A? - answer- 60 days
Consider the following work breakdown structure:
Time Estimates (days)
ActivityPrecedesOptimisticMost LikelyPessimisticStartA,B,C - - - AD 38 50 62 BE 90 99
108 CEnd 85 100 115 DF 19 25 31 EEnd 91 100 115 FEnd 62 65 68
What is the probability that this project will be completed within 205 days - answer-
0.8413
Consider the portion of a project depicted by this graph: What is the earliest finish time
for activity 10-11 (far right-hand side) if the earliest start time of 8-10 (upper left-hand
side) is 12 and the earliest start time of 9-10 (lower left-hand side) is 13? - answer- 23
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.49. You're not tied to anything after your purchase.