100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
NERC EXAM QUESTIONS AND ANSWERS $10.99   Add to cart

Exam (elaborations)

NERC EXAM QUESTIONS AND ANSWERS

 1 view  0 purchase
  • Course
  • NERC
  • Institution
  • NERC

NERC EXAM QUESTIONS AND ANSWERS

Preview 2 out of 7  pages

  • August 10, 2024
  • 7
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • NERC
  • NERC
avatar-seller
GEEKA
NERC EXAM QUESTIONS AND ANSWERS
A Balancing Authority notices that Operating Reserve has steadily declined throughout
the hour. What is the most likely cause?

a) Loss of a large generator in the area
b) An inaccurate load forecast
c) Loss of a major transmission line
d) A malfunction of EMS - answer- b) An inaccurate load forecast

Balancing Area A notices that the Interconnection frequency is 59.94 Hz and their ACE
is 0. Which of the following could be the cause of this reading?

a) A net under-generation in Balancing Area A
b) A net under-generation in the Interconnection
c) A loss of load in Balancing Area A
d) A loss of load in the Interconnection - answer- b) A net under-generation in the
Interconnection

What is the penalty for a Balancing Authority violating the Disturbance Control
Standard?

a) Must carry additional Contingency Reserve
b) Must develop a correction action plan
c) Must re-evaluate and change its Frequency Bias Setting
d) Must increase its Regulating Reserve - answer- a) Must carry additional Contingency
Reserve

Your ACE is a large negative value and system frequency is 59.80 Hz. Your AGC
system is pulsing your units down. What should you do?

a) Place AGC in flat frequency control
b) Place AGC in flat tie line control
c) Suspend AGC and investigate
d) Do nothing as this is normal - answer- c) Suspend AGC and investigate

When two identical generating units are operated in parallel on governor control, and on
machine has a 5% droop and the other has a 10% droop, the unit with the greater
(10%) governor droop will:

a) Respond less to frequency deviations
b) Respond more to frequency deviations
c) Respond the same to frequency deviations
d) Not adjust for frequency changes - answer- a) Respond less to frequency deviations

, On a radial transmission system a generator has a capacity of 600 MWs. The Droop
characteristic is at 5% and the generator is currently loaded at 300 MWs. If frequency
suddenly drops to 59.3 Hz, what would be the total generator output?

a) 350
b) 400
c) 440
d) 600 - answer- c) 440

What is the main purpose of the Frequency Bias Setting in the ACE equation?

a) Control frequency to 60 Hz for the entire Interconnection
b) Assist with arresting frequency deviations
c) Restore frequency to 60 Hz after a disturbance
d) maintains frequency between 59.95 and 60.05 Hz - answer- b) Assist with arresting
frequency deviations

In a permissive protective relay scheme, the term "permissive" refers to:

a) The receipt of a telecommunications signal from the opposite line terminal
b) The process of automatic re-testing of a tripped line section
c) The system operator granting permission for a line to trip
d) The enabling of an automatic reclosing scheme - answer- a) The receipt of a
telecommunications signal from the opposite line terminal

The NERC standards require the use of three-part communication when issuing and
receiving Operating Instructions. Which of the following would fall into that category?

a) A discussion with the RC about a possible contingency
b) Switching instruction s to a field operator
c) Two Transmission Operators discussing in a System Operating Limit
d) A System Operator reporting system conditions to his supervisor - answer- b)
Switching instructions to a field operator

A Balancing Authority receives an Operating Instruction from its Reliability Coordinator.
The Balancing Authority must comply with the Operating Instruction unless:

a) It results in separation from the Interconnection
b) The Balancing Authority disagrees with it
c) Has serious financial implications
d) Results in danger - answer- d) Results in danger

Which of the following is extremely important in determining system load when
performing a next day study:

a) Transmission configuration

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

83637 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.99
  • (0)
  Add to cart