Your answers
1 of 147
Term
What cost estimation method takes cost per person-hour, square
meter or foot from provider quotes, and historical costs and then
multiplies this rate by the quantity of the resource?Which of the
following is a cost estimation method that takes cost per person-hour,
square meter or foot from provider quotes and historical costs and
then multiplies this rate by the quantity of the resource?
,Give this one a try later!
Parametric modeling Additive method
Solid modeling Digital sculpting
Don't know?
2 of 147
Term
What is true of quality management?
Give this one a try later!
If costs need to be reduced,
quality management ensures
Quality management focuses solely
that grade is reduced if
on increasing costs.
approved as a scope change
but quality is maintained.
Quality management has no impact Quality management is only
on project outcomes. concerned with quantity, not quality.
Don't know?
3 of 147
,Term
What is done after defining a project's purpose and could be
accomplished using a tool such as the project triangle?
Give this one a try later!
Planned iteration. Test the purpose for feasibility.
Incomplete work on the site is Keep the contract open and provide
acceptable if they are areas prepared a letter indicating the unmet criteria
for owner-furnished items. and required actions.
Don't know?
4 of 147
Term
Which scheduling methods are for activities NOT concurrently
performed?
Give this one a try later!
Construction management Multiple prime contracts approach
Location of remote workers
, Traditional waterfall model
scheduling
Don't know?
5 of 147
Term
An owner suggests an alternative material be used in a project. What
would this request involve?
Give this one a try later!
Construction change directive Scope of work
Amendment Change order
Don't know?
6 of 147
Term
What does a project manager need to be successful?
Give this one a try later!
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller TheAlphanurse. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $17.99. You're not tied to anything after your purchase.