Unit of work performed by one person in 8
hours - answer What is a Man-Day?
- Project Supervisor and Crew Leads review
the plans with the drawings
- Project Sup and Crew Leads prep a project
package scope sheet and send it to S3
, - Project sups create a project scope sheet
with information and pictures of the site -
answer Define what a Project Scope is.
All labor, in the field or shop, directly related
to the assigned task - answer Define Direct
Labor
All labor in support of a project but usually
doesn't produce an end product - answer
Define Indirect Labor
Preparations for military exercises and
disaster preparedness. - answer Define
Readiness and Training
It calculate how many extra Man-Days are
needed for a project - answer What does a
Delay Factor do?
- MC= DL x WD x ME x AF
- MC: Total Man-Day capiblity
- DL: Number of Direct Labor Personnel on a
project
Warfare SCW
(NMCB Specific
109 Construction
Operations
Fundamentals)
Unit of work performed by one person in 8
hours - answer What is a Man-Day?
- Project Supervisor and Crew Leads review
the plans with the drawings
- Project Sup and Crew Leads prep a project
package scope sheet and send it to S3
, - Project sups create a project scope sheet
with information and pictures of the site -
answer Define what a Project Scope is.
All labor, in the field or shop, directly related
to the assigned task - answer Define Direct
Labor
All labor in support of a project but usually
doesn't produce an end product - answer
Define Indirect Labor
Preparations for military exercises and
disaster preparedness. - answer Define
Readiness and Training
It calculate how many extra Man-Days are
needed for a project - answer What does a
Delay Factor do?
- MC= DL x WD x ME x AF
- MC: Total Man-Day capiblity
- DL: Number of Direct Labor Personnel on a
project