What Component of LMP is the same for every bus in the PJM RTO? - answer System
Energy Price
What control signal is measured in MWs? - answer Economic basepoint
Which of the following are the two Ancillary Service Markets that PJM operates? -
answer Regulation and Synchronized Reserve markets
Who regulates PJM? - answer Federal Energy Regulatory Commission (FERC)
A Geomagnetic Disturbance Warning issued by PJM when the NOAA has issued a
warning or an alert for a potential GMD storm of what severity? - answerK7
During an Environmental Emergency Act Emergency, which entity must submit for the
request for variance to the appropriate government agency? - answerThe Generation
Owner
Warning issued when synch reserve requirements are less than synch reserve
requirement - answerVoltage reduction warning and Reduction of of Non-critical plant
load.
The purpose of the Heavy Load Voltage Schedule Warning is to have members prepare
for maximum support of voltages on the : - answerBulk Power System
During a suspected terrorism or sabotage event, PJM puts emphasis on what aspects
of operation? - answerOperation and Communication
PJM can issue Emergency Procedures in any order to keep reliable operations in the
RTO. The normal sequence of issuing Deploy All Resources is after: - answerissued
prior but no later than the same time as a Voltage Reduction Action
During a Heavy Load Voltage Schedule Action, all Generation Owners/Operators will be
directed to: - answerMaintain a MVAR reserve on units connected at the EHV level
What information does PJM provide to members during a Minimum Generation Alert? -
answer-Adjusted Minimum Generation
-Valley and Load estimate
What Component of LMP is the same for every bus in the PJM RTO? - answer System
Energy Price
What control signal is measured in MWs? - answer Economic basepoint
Which of the following are the two Ancillary Service Markets that PJM operates? -
answer Regulation and Synchronized Reserve markets
Who regulates PJM? - answer Federal Energy Regulatory Commission (FERC)
A Geomagnetic Disturbance Warning issued by PJM when the NOAA has issued a
warning or an alert for a potential GMD storm of what severity? - answerK7
During an Environmental Emergency Act Emergency, which entity must submit for the
request for variance to the appropriate government agency? - answerThe Generation
Owner
Warning issued when synch reserve requirements are less than synch reserve
requirement - answerVoltage reduction warning and Reduction of of Non-critical plant
load.
The purpose of the Heavy Load Voltage Schedule Warning is to have members prepare
for maximum support of voltages on the : - answerBulk Power System
During a suspected terrorism or sabotage event, PJM puts emphasis on what aspects
of operation? - answerOperation and Communication
PJM can issue Emergency Procedures in any order to keep reliable operations in the
RTO. The normal sequence of issuing Deploy All Resources is after: - answerissued
prior but no later than the same time as a Voltage Reduction Action
During a Heavy Load Voltage Schedule Action, all Generation Owners/Operators will be
directed to: - answerMaintain a MVAR reserve on units connected at the EHV level
What information does PJM provide to members during a Minimum Generation Alert? -
answer-Adjusted Minimum Generation
-Valley and Load estimate