APMP Foundation Exam Q & A Verified Solutions
Q.1 A kick-off meeting is ... - needed only if the team is distributed over several locations - only for those who provide content - only for top management members - a meeting where all stakeholders are invited.
Q.2 Which of the following guidelin...
- needed only if the team is distributed over several locations
- only for those who provide content
- only for top management members
- a meeting where all stakeholders are invited. ✅
Q.2 Which of the following guidelines is generally seen as best practice?
- Allow 30-40% of total time for final review, amendment, and production
- Allow 15% of total time for start-up and planning ✅
- Schedule 20% contingency time
- Allow 10-20% of total time for kick-off preparation and proposal strategy review (earlier called the pink
review)
Q.3 Which is correct?
- The Win Rate is the value ($) of the bids submitted, divided by the value ($) of the bids won
- The Capture Ratio is the number of bids won, divided by the $ value of the bids submitted
- The Capture Ratio is the value ($) of the bids submitted, divided by the number of bids won
- The Win Rate is the number of bids won, divided by the number of bids submitted ✅
Q.4 To produce a complex graphic, it typically needs
- 20 minutes each
- 1 hour each
- 2—6 hours each ✅
- 1 day each
Q.5 Which of the following elements are typically NOT found in a proposal cost budget?
,- Facilities
- Bid production costs
- Contributors
- Advertising ✅
Q.6 According to best practice, how much time should you allocate for final review, amendment, and
production?
- Less than 10% of the available time
- 10-20% of the available time ✅
- 20-30% of the available time
- 40-50% of the available time
Q.7 Which of the following statements is correct?
- The Business Case Review is before the Kick-Off Meeting
- The Kick-Off Meeting is before the Proposal Strategy Review (also called Storyboard Review or Content
Plan Review) ✅
- The Final Document Review is after bid submission
- The Opportunity Plan Review (earlier called Strategy Review, or Blue Review) is after the Kick-Off
Meeting
Q.8 What is the right planning sequence?
- Market Identification after Opportunity Assessment
- Opportunity Planning before Proposal Planning before Proposal Preparation ✅
- Opportunity Planning after Opportunity Assessment
- None of the above
Q.9 How much time do you calculate for contingency, Final Document Review, amendment, and
production?
- 20-30%
- 30-40%
, - 5%
- 10% ✅
Q.10 A good proposal development process should always ...
- Be documented in Microsoft Visio
- Be designed in a way that no training is needed
- Be "owned" by one person
- Contain no parallel tasks ✅
Q.11 As the kick-off meeting organizer, which of the following would you NOT do?
- Invite Final Document Reviewers
- Develop Content Plan during the kick-off meeting ✅
- Present action plan for proposal process
- Present competition overview
Q.12 Which of the following is TRUE for kick-off meetings?
- Never invite a top management member. It is too early.
- Never invite production specialists. It is too early.
- Never invite graphics designer.
- Provide relevant RFP sections to meeting participants in advance, if helpful. ✅
Q.13 Which data does a proposal manager require for a qualification meeting?
- Customer details and requirements, win strategy, cost of winning the business, degree of risk,
competition details and offerings, capabilities of our organization to meet requirements, proposal
templates
- Win strategy, cost of winning the business, degree of risk, complete kick-off package, capabilities of our
organization to meet requirements
- Customer details and requirements, competition details and offerings, capabilities of our organization
to meet requirements, cost of winning the business, win strategy, degree of risk
- RFP, recent proposals, competition details, and offerings ✅
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller CertifiedGrades. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.89. You're not tied to anything after your purchase.