100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PRM3701 ASSIGNMENT 3 semester 2 2024 Identify the critical path a. ACEFIJ b. ABDGIJ c. ABEFI d. ABEFIJ e. ACEHIJ What is the late nish (LF) time for activity J? a. 19 b. 18 c. 17 d. 16 e. 15 $2.86   Add to cart

Exam (elaborations)

PRM3701 ASSIGNMENT 3 semester 2 2024 Identify the critical path a. ACEFIJ b. ABDGIJ c. ABEFI d. ABEFIJ e. ACEHIJ What is the late nish (LF) time for activity J? a. 19 b. 18 c. 17 d. 16 e. 15

 112 views  8 purchases
  • Course
  • Institution
  • Book

PRM3701 ASSIGNMENT 3 semester 2 2024 Identify the critical path a. ACEFIJ b. ABDGIJ c. ABEFI d. ABEFIJ e. ACEHIJ What is the late nish (LF) time for activity J? a. 19 b. 18 c. 17 d. 16 e. 15

Preview 3 out of 25  pages

  • August 19, 2024
  • 25
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
avatar-seller
BMZ ACADEMY




BMZ ACADEMY




@061 262 1185/068 053 8213



BMZ ACADEMY 061 262 1185/068 053 8213

, UNISA  2024  PRM3701-24-S2  Welcome Message  Assessment 3

QUIZ




Question 1

Not yet answered

Marked out of 1.00




What is the earliest start (ES) time for activity G?


a. 5

b. 7

c. 9

d. 11

e. 17




Question 2
Not yet answered

Marked out of 1.00




What is the late finish (LF) time for activity F?


a. 17
b. 16

c. 21

d. 19

e. 7




Question 3

Not yet answered

Marked out of 1.00




What is the late finish (LF) time for activity E?


a. 9

b. 13

c. 15

d. 14

e. 7

, Question 4

Not yet answered

Marked out of 1.00




What is the late finish (LF) time for activity H?


a. 17

b. 12

c. 14

d. 19

e. 9




Question 5

Not yet answered

Marked out of 1.00




Which activity has a slack of 10 days?


a. Activity D

b. Activity E

c. Activity H

d. Activity J

e. None of the above




Question 6
Not yet answered

Marked out of 1.00




Determine the duration it will take to complete this project using the AON method.


a. 19 days

b. 20 days

c. 14 days

d. 9 days

e. 11 days




Question 7
Not yet answered

Marked out of 1.00




If Activity F is delayed by 2 days. What will happen to the rest of the project?


a. The whole project will be delayed by 2 days

b. There will be no impact on the project

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller BMZAcademy. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $2.86. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75759 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling

Recently viewed by you


$2.86  8x  sold
  • (0)
  Add to cart