. All of the following are included in an Agile project charter, except for which one? a) Detailed project scope b) Expected ROI c) Signature and date d) Project goals and objectives: a) Detailed project scope 2. Agile team members have identified a risk in a project and are not able to resolve it ...

[Show more]

Preview 4 out of 38  pages

  • August 19, 2024
  • 38
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • cmgt 410
All documents for this subject (7)
avatar-seller
jacksonruth
CMGT 410

CMGT 410 - Wk 5 - Apply: Post-Test
All of the following are included in an Agile project charter, except for which one?
a. Detailed project scope
b. Expected ROI
c. Signature and date
d. Project goals and objectives: correct answer- a) Detailed project scope

Agile team members have identified a risk in a project and are not able to resolve it due to lack of
expertise. You, as a Agile project manager, decided to contract with a third party for resolving the risk.
Which of the following risk response strategies have you applied?
a. Accept
b. Avoid
c. Transfer
d. Mitigate: correct answer-c) Transfer

When the customer is thinking and explaining something one way and the team takes it in a different
way. This is referred to as which of the following?
a. The gulf of understanding
b. The gulf of misunderstanding
c. The gulf of Agile
d. The gulf of evaluation: correct answer-a) The gulf of understanding

An Agile team working together on a project are sitting in a big meeting room. In the room, John was
discussing with Kim about a security loophole while implementing the code design for a module. In
between, Harry, who was listening to their discussion gets an idea on the improvement of current code
design and notes it down for further design discussion meeting with architects. He asks John and Kim to
park this code implementation for a while and requests them to continue code development of the
remaining module.
According to the given scenario, this is referred to as which of the following?
a. Osmotic communication
b. Emotional intelligence
CMGT 410

,CMGT 410
c. Nonverbal communication
d. Mirroring: correct answer- b) Emotional intelligence


As an Agile project manager, you want to perform a review of your project from several different
characteristics. You would like to review what worked on the project and what needed improvement.
Which of the following will you use to accomplish the task?
a. Kano analysis
b. MoSCoW
c. Shu Ha Ri
d. SWOT analysis: d) SWOT analysis

Using the following values: earned value = 8,000 planned value = 4,000, actual cost = 3,000, calculate
CV (cost variance).
a. 5,000
b. 4,000
c. 1,000
d. 2,000: a) 5,000

Which of the following is a performance measure, used for evaluating gain or loss generated on an
investment relative to the amount of money invested?
a. IRR
b. INVEST
c. ROI
d. NPV: c) ROI

All of the following are examples of special causes, except for which one?
a. Machine malfunctioning
b. Measurement errors
c. Faulty controllers
d. Computer crashing: b) Measurement errors
CMGT 410

,CMGT 410

In a planning poker session, the cards used are presented with which of the following series for assessing
story points?
a. Arithmetic progression
b. Fibonacci
c. Even
d. Odd: b) Fibonacci

A technique in which multiple team members focus collectively on resolving a specific impediment is
referred to as:
a. Tailoring
b. Grooming
c. Swarming
d. Refactoring: c) Swarming

What is the primary purpose of the retrospective meeting?
a. Discuss what went well, what didn't got so well, and what improvements could be made
immediately in the next iteration.
b. Identify what was learned during the project/program.
c. Demonstrate the completed work to the customer for gaining their feedback and for encouraging
collaboration
d. Discuss and review team practices openly and assess how the team is working together.: a) Discus
what went well, what didn't got so well, and what improvements could be made immediately in the
next iteration.

According to the Agile Manifesto, which of the following is an accurate practice?
a. Contract Negotiation over Customer Collaboration
b. Comprehensive Documentation over Working Software
c. Individuals and Interactions over Processes and Tools
d. Following a Plan over Responding to Change: c) Individuals and Interactions over Processes and
Tools

CMGT 410

, CMGT 410

The Shu Ha Ri model depicts the maturity of learning and application in a team environment. What is the
meaning of the word Sha Ha Ri?
a. Leave, be the rule; learn, follow the rule, detach, break the rule
b. Detach, break the rule; leave, be the rule; learn, follow the rule
c. Learn, follow the rule; detach, break the rule; leave, be the rule
d. Detach, break the rule; separate, be the rule; learn, follow the rule: c) Learn, follow the rule;
detach, break the rule; leave, be the rule

A planning is done at three distinct horizons using which of the following?
a. Wireframe
b. Prototyping
c. Progressive elaboration
d. Kano analysis: c) Progressive elaboration

As an Agile project manager, you are planning a seating arrangement for your project team. You want
that the team sits together in the work area and sees each other. What is the purpose of this arrangement?
Helping the product owner to attend the daily stand-ups
Making the optimum use of available space
Helping a team to see what the other person is doing
Helping in osmotic communication: d) Helping in osmotic communication

You ask the customer to give out fake amount to individual business features to better understand the
project's goal. This is referred to as which of the following?
a. Dot voting
b. Monopoly money
c. MoSCoW
d. 100-point method: b) Monopoly money

In a discussion between two Agile team members, one of the team mem- bers is showing positive
gestures, nodding his head, and asking questions. This is an example of which of the following?
a. Emotional intelligence

CMGT 410

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller jacksonruth. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.00. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

67866 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.00
  • (0)
  Add to cart