Answers.
In construction drawings, line indicating hidden or future construction,
or construction to be removed (BCE page 152)
Correct Answer -dotted
Setback is the difference from the building to (BCE page 158)
Correct Answer -the property line
Standards referenced in the international building code are considered
(IBC page 2)
Correct Answer -part of the requirements of the codes to be prescribed
For materials or assemblies not specifically covered by the IBC, the
supporting data must include... (IBC page 3)
Correct Answer -valid research from approved sources
List of criteria satisfied before modification to the IBC requirements for
flood hazard area is permitted (IBC page 3?)
Correct Answer -a determination that failure to grant the variance would
result in exceptional hardship by rendering the lot undevelopable
Test reports shall be retained when tests are required as evidence of
compliance with the IBC (IBC page 4)
Correct Answer -for the period required for the retention period
, Maximum height for a fence for exemption from permit requirements
(IBC page 4)
Correct Answer -7 feet
Approved permit expires if no work has commenced (IBC page 5)
Correct Answer -108 days
Construction documents designated number of occupants for all floors,
rooms, and spaces (IBC page 6)
Correct Answer -means of egress
In commercial and industrial buildings, posting of live load in which
areas (IBC page 6)
Correct Answer -exceeding 50 psf
permit for a temporary structure shall be valid for (IBC page 7)
Correct Answer -180 days
boards of appeals authority (IBC page 9)
Correct Answer -appointed by the applicable governing authority
difference between group 1-1 and group 1-2 occupancy (IBC page 41)
Correct Answer -intended use
ambulatory care facility classified as which occupancy (IBC page 41)
Correct Answer -business group B