Give a description of the CDM Regulations Correct Answer-The CDM
Regulations provide a framework for managing Health and Safety during the
construction, repair, maintenance and demolition of building works.
Who are affected by the CDM regul...
CDM Regulations; Questions and Answers
100% Solved
Give a description of the CDM Regulations Correct Answer-The CDM
Regulations provide a framework for managing Health and Safety during the
construction, repair, maintenance and demolition of building works.
Who are affected by the CDM regulations? Correct Answer-1. Anyone
involved in a construction project.
2. Clients - anyone who has construction work carried out for them.
3. Principal Designer - Appointed by the client on projects with more than 1
contractor - duty is to manage, monitor and co-ordinate the health and safety
during the pre-construction phase.
4. Designers - An organisation or individual who is involved in preparing or
modifying drawings, designs, specifications, bills of quantities, design
calculations. - Main duty is to eliminate, reduce or control foreseeable risk
(during construction or maintenance)
5. Contractors
What are the principal objectives of the CDM Regulations? Correct Answer-1.
To place H&S at the heart of the construction process from initial design to final
account and beyond.
2. Sensibly
3. To co ordinate communication between all parties to the construction
, CDM Regulations; Questions and Answers
100% Solved
4. To ensure adequate resources, including time, are given to H&S matters
5. To ensure that competent people only are appointed.
6. To involve and share responsibility between all the parties.
When do projects not fall under the CDM regulations? Correct Answer-CDM
Regulations apply to all construction projects, including domestic.
When should the HSE be notified of works? Correct Answer-When the works
last longer than:
• 30 Days and more than 20 persons working at the same time at any point in
the contract
• Exceeding 500 person days
When should HSE notification be made? Correct Answer-The client (or
contractor/principal contractor is a domestic project) as soon as it is practicable
before the construction phase begins.
The PD may assume the responsibility of sending the F10 Notice, if written
instruction is provided by the client.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller TheeGrades. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.99. You're not tied to anything after your purchase.