100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
C722 Questions and answers verified 2024 $13.49   Add to cart

Exam (elaborations)

C722 Questions and answers verified 2024

 3 views  0 purchase
  • Course
  • WGU C722
  • Institution
  • WGU C722

C722 Questions and answers verified 2024

Preview 4 out of 85  pages

  • August 28, 2024
  • 85
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • WGU C722
  • WGU C722
avatar-seller
LEWISSHAWN55
C722- Project Management, WGU C722
(Pre), WGU C722 Project Management
Terminology, WGU C722 Project
Management Terminology, WGU C722
Equations
A firm begins its strategic business initiative of developing a new business
model that will allow the firm to deliver an efficient, tailored service to its
customers. To accomplish this, the firm initiates a business management
project. Which aspect of project management applies to this firm's project? -
correct answer ✔Interdependent Tasks


A firm begins its strategic business initiative of developing a new business
model to enhance its competitiveness. What can be identified as a strategic
business initiative for this firm? - correct answer ✔Improvement in product
design


A firm begins a strategic business initiative of developing a new business
model that will allow the firm to deliver an efficient, tailored service to its
customers. - correct answer ✔Project sponsor


Which group is included in the five process groups? - correct answer
✔Closing process group


What does PRINCE2 stand for? - correct answer ✔PRojects IN a Controlled
Environment


Which PMBOK process group is described as the delivery part of project
management where the main activity happens? - correct answer ✔Executing

,Which advantage does the functional (departmentalized) organizational
structure provide for a firm with multiple projects? - correct answer ✔Lines of
authority are clear.


Which two organizations are examples of organizations with the functional
organizational structure? - correct answer ✔(1) The U.S. Department of
State and (2) The U.S Department of Energy


An organization expects to use a project management office (PMO) to support
multiple projects that will be implemented within a projectized organizational
structure. Which implied effect is a benefit to this organization? - correct
answer ✔Project team members gain access to historical data from other
projects.


Regardless of the organizational structure used to manage a project, an
organization elects to use a project management office (PMO). Which benefit
will this organization gain? - correct answer ✔Projects will coordinate
resource usage by monitoring the status of shared resources.


During a certain project phase, specific blueprints are drawn and approved,
materials and labor costs are estimated, prototypes are created, and work
activities and tasks are identified. Also, quality expectations, measurements,
and costs are defined. During which project phase do these activities occur? -
correct answer ✔Planning


Place the project activities in order of occurrence from first (1) to last (5). -
correct answer ✔(1) Collecting customer requirements (2) Developing the
work breakdown structure (3) Working to produce project deliverables (4)
Customers evaluating the project outcomes (5) Capturing lessons learned

,During which life cycle phase is the vast majority of the actual work to produce
the project's deliverables completed? - correct answer ✔Executing


What is the correct term for an intermediate outcome of project work, such as
a signed contract or obtaining a construction permit? - correct answer
✔Deliverable


Which deliverable from a work breakdown structure (WBS) is not specific
enough to measure its completion at project closure? - correct answer
✔User training


The following table shows the Level 1 work breakdown structure (WBS) for
Project A.


WBS ID Description
0.0 Project A
1.0 Project started
2.0 Feasiblity
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
Which approach did the project manager use to structure the WBS? - correct
answer ✔Sequence of project phases


For the following collapsed work breakdown structure (WBS) for Project O, the
project manager must complete the scope baseline. In addition to the WBS,
the scope baseline will contain two additional documents.

, WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
What are the other two documents that belong in the scope baseline? -
correct answer ✔WBS dictionary and project scope statement


For the following collapsed work breakdown structure (WBS) for Project O, the
project's steering committee held a phase gate review of the Feasibility
results. That review determined that the project's proposed design would be
obsolete before it would reach the marketplace.


WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller LEWISSHAWN55. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79271 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.49
  • (0)
  Add to cart