WGU C722 (Pre)
PMBOK 5 Process Groups - correct answer ✔Initiating, Planning (Iterative),
Executing (Iterative), Monitor & Control (Iterative) and Closing
Triple constraint - correct answer ✔Time, Cost, and Scope
Organizational Project Management Maturity Model (OPM3) 5 levels
(Delaware Department of Technology and Information) - correct answer ✔1)
"Adhoc" 2) "Planned" but no org standard 3) "Managed" but execution is
inconsistent 4) "Integrated" is consistent 5) "Sustained" is consistent, can
evaluate future decisions and includes lessons learned
5 levels of project management maturity (Crawford, 2007) - correct answer
✔1) Initial 2) Structured standards 3) Organizational standards 4) Managed
Process 5) Optimized process
Initiating (Process #1) - correct answer ✔Define the project and determine
which projects the organization will undertake. These activities often occur
prior to the selection of the project team or the project manager.
Initiating Activities (Process #1) - correct answer ✔Document business need,
define project, evaluate proposals, complete project selection, identify
stakeholders, and create project charter
Which activity is preformed during the creating part of the initiating process? -
correct answer ✔Drafting project chater
Planning (Process #2 - Iterative) - correct answer ✔PM will assemble a team
to create the project plan. Additional team members may be required to gather
, information from stakeholders, identify the project activities, estimate costs
and time, and document the planning areas
Planning Activities (Process #2 - Iterative) - correct answer ✔Document
customer needs, estimate resource, scope, budget, schedule, WBS (Work
Breakdown Structure), Network Diagram, activity list, and writing plan for orgs
to execute
Tool for PM to track that important items are addressed when developing and
defining project scope? - correct answer ✔Network diagram
WBS (Work Breakdown Structure) - correct answer ✔Lists the project
activities and tasks and begins to identify how they fit together and where they
fit on a calendar
Executing (Process #3 - Iterative) - correct answer ✔PM cycles members as
needed to create the project outcomes
Monitor & Control (Process #4 - Iterative) - correct answer ✔Assess whether
project plan is implemented, outcomes and deliverables are as expected.
Also, to get the project team back on the plan or make adjustments to the plan
in order to achieve the desired outcomes and deliverables
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller LEWISSHAWN55. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.