addenda should include all but which of the following - ANSWER --revisions to owner contractor
agreement
t/f; only the owner has authority to direct a change in contract documents - ANSWER --true
change order should contain all but wh...
BCN3761 EXAM| with 100% Correct
Answers| Latest Update 2024
addenda should include all but which of the following - ANSWER --revisions to owner contractor
agreement
t/f; only the owner has authority to direct a change in contract documents - ANSWER --true
change order should contain all but which of the following - ANSWER --change in bid date
and location
t/f; a construction change directive (AIA contract documents) or work directive (EJCDC
contract documents) requires the contractor to immediately comply with the required changes
- ANSWER --true
t/f; architect supplemental instruction may be used to change the contract time and contract
sum - ANSWER --false
t/f; standard forms for change orders are published by the american institute of architects
(AIA) and by the engineers joint contract documents committee (EJCDC) - ANSWER --true
, t/f; division 01 general requirements apply to all specifications in divisions 02 through 49
- ANSWER --true
bidding requirements covered in division 01 general requirements include all but which of
the following - ANSWER --bid bond
which of the following is untrue regarding division 01 general requirements - ANSWER --division
01 general requirements modify the general conditions
t/f; division 01 general requirements and the drawings should be coordinated - ANSWER --true
t/f; division 01 general requirements specifications are written in 3 part section format
similar to sections in divisions 02 - 49 - ANSWER --true
t/f; facility commissioning requirements are included in division 01 general requirements -
ANSWER --true
t/f; requirements for administering shop drawing and product data submittals are specified in
division 01 general requirements - ANSWER --true
which of the following is not specified in division 01 general requirements - ANSWER --delivery
requirements for door hardware
t/f; the scale and sheet size for structural steel shop drawings are specified in division 01
general requirements - ANSWER --false
administrative requirements for preparation and issuance of bid addenda are specified in
division 01 general requirements - ANSWER --false
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller KenAli. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.49. You're not tied to anything after your purchase.