100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PMP Practice Questions And Answers 100% Solved $13.99   Add to cart

Exam (elaborations)

PMP Practice Questions And Answers 100% Solved

 6 views  0 purchase
  • Course
  • PMP
  • Institution
  • PMP

PMP Practice Questions And Answers 100% Solved Project started out with 8 members. Then increased by 6 additional members. How many communication channels were added to the project? a) 91 b) 63 c) 28 d) 15 Correct Answer-B) 63

Preview 3 out of 30  pages

  • August 29, 2024
  • 30
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • PMP
  • PMP
avatar-seller
TheeGrades
PMP Practice Questions And Answers 100%
Solved
Project started out with 8 members. Then increased by 6 additional members.
How many communication channels were added to the project?
a) 91
b) 63
c) 28

d) 15 Correct Answer-B) 63


Which of the following would result in a change request?


a) A major delay of non critical path activity
b) An overall SPI of 1.05
c) An overall SPI of 1

d) A short delay of a critical path activity Correct Answer-d) A short delay of a
critical path activity


What is the schedule variance of this project? Total cost is $205,000; After 5
weeks, it is half a week ahead of schedule and the cost is currently $143,000.
a) 260,000
b) 10,250
c) -10,250

d)-55,000 Correct Answer-b) 10,250


An expert has assured you that the cost to replace insulation is $15,000,. Where
you document the reasons these corrective options were chosen?

, PMP Practice Questions And Answers 100%
Solved
a) Lessons Learned
b) Change Log
d) Project Records

e) Assumptions Log Correct Answer-a) Lessons Learned


You are the project manager for a project that is taking 3 times longer on a
phase than expected. You decide to contract out the work to ensure the project
deadline is not exceeded. What best decides what you are doing?
a) Fulfilling a project scope change
b) Performing a corrective action
c) Performing a defect repair

d) Performing a preventative action Correct Answer-b) Performing a
corrective action


You are the project manager. After reviewing procurement documents, you
notice that there are not any available vendors. What should you do?
a) Submit a request for proposal
b) Create a request for information and publish it in the local newspaper
c) Obtain expert judgement for the current situation

d) Book a conference center and hold a bidder conference Correct Answer-b)
Create a request for information and publish it in the local newspaper


You are the project manager and one of your team members is working on a
medium project task. The member seems distracted and is falling behind on his
work. Which is the best option?

, PMP Practice Questions And Answers 100%
Solved
a) Observe the situation closely
b) Reprimand the worker and place them on another project
c)Recommend the member take the day off and reassign the work to another
team member

d) Get the worker to work extra time to make up the work. Correct Answer-c)
Recommend the member take the day off and reassign the work to another
team member


What documents are typically referenced during the closing of a project. Choose
the BEST answer.
a) Project baselines
b) Scope statement
c) Lessons Learned

d) Project Management Plan Correct Answer-d) Project Management Prlan


A flood has occurred. The risk response plan does not cover this type of disaster,
therefore a procedure on how to handle this is not documented. Which item
should be used to address this issue?
a) Alternatives generation
b) Contingency reserve
c) Workaround

d) Management reserve Correct Answer-c) Workaround


You are working on a budget. Which item is BEST used to help you determine
more accurate estimates of what activities will cost?

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller TheeGrades. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

67096 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.99
  • (0)
  Add to cart