1. All of the following are characteristics of a project except A. It is temporary B. It has a definite beginning and end C. It creates a unique product D. It repeats itself every month Answer: D It repeats itself every month "It repeats itself every month" implies that the whole project r...

[Show more]

Preview 2 out of 10  pages

  • September 3, 2024
  • 10
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • BMGT
  • BMGT
avatar-seller
tuition
SCM 472 CAPM Exam question with
complete solution



1. All of the following are characteristics of a project except
A. It is temporary
B. It has a definite beginning and end
C. It creates a unique product
D. It repeats itself every month - ANSWER- Answer: D
It repeats itself every month

"It repeats itself every month" implies that the whole project repeats every month.
Generally, the only things that might repeat in a project are some activities. The
entire project does not repeat.

2. Which of the following statements about the project manager is true?
A. The project manager provides subject matter expertise
B. The project manager ensures buy-in and gathers support for the project
throughout the organization
C. The project manager is responsible for managing the project to meet project
objectives and deliver value
D. The project manager determines the priorities between project constraints -
ANSWER- Answer: C
The project manager is responsible for managing the project to meet project
objectives and deliver value

The project manager is responsible for managing the project objectives and
deliver value to the organization. The functional or resource manager provides
subject matter expertise, and the project sponsor is responsible for ensuring buy-
in, gathering support, and determine the priorities among the project contraints.

3. Who has the most power in a project-oriented organization?
A. The project manager
B. The functional manager
C. The team
D. They all share power equally - ANSWER- Answer: A

, The project manager

In a project-oriented organization, the entire company is organized by projects,
giving the project manager the most power

4. What is a program?
A. The same thing as a project
B. A group of related projects
C. A group of small projects and related operational work
D. Ongoing operations rather than project work - ANSWER- Answer: B
A group of related projects

A program is a group of related projects; It does not include operational work.
Grouping such projects into a program can help an organization reduce risk and
achieve economies of scale. Programs also improve management by providing
coordinated control, support, and guidance across multiple projects

5. A project team member is concerned because many people are asking him to
do things. If he works in a functional organization, who has the power to give him
direction?
A. The project manager
B. The functional manager
C. The team
D. The PMO - ANSWER- Answer: B
The functional manager

In a functional organization, the team member report to the functional manager.
The project manager probably reports to the functional manager as well.

Operational work is different from project work in that operational work is:
A. Unique
B. Temporary
C. Ongoing and repetitive
D A part of an everyday activity - ANSWER- Answer: C
Ongoing and repetitive

Operational work is work that is being done on an operational basis to sustain an
organization, while a project is a temporary endeavor, with a beginning and an
end, that creates a unique result.

In a project-oriented organization, the project team:

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller tuition. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77988 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.99
  • (0)
  Add to cart