100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
DBIA Test Exam 2024 | DBIA Actual Exam Questions and Correct Answers Rated A+ $25.55   Add to cart

Exam (elaborations)

DBIA Test Exam 2024 | DBIA Actual Exam Questions and Correct Answers Rated A+

 3 views  0 purchase
  • Course
  • Institution

DBIA Test Exam 2024 | DBIA Actual Exam Questions and Correct Answers Rated A+

Preview 4 out of 33  pages

  • September 5, 2024
  • 33
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
avatar-seller
DBIA Test Exam 2024 | DBIA Actual
Exam Questions and Correct Answers
Rated A+
How team members are organized, establishes when parties engage,
determines roles of parties, and determines sequence of design,
procurement, and construction (db, cmar, dbb) -ANSWER-Project
Delivery System

How team members are selected (QBS, best value, low price, sole
source) -ANSWER-Procurement Method

How team members are paid (fp, gmp, cost reimbursement, target
price, unit price) -ANSWER-contracting approach

Linear, sequential process, A/E selected on qualifications, GC
selected on low price, design is fully completed without input from GC,
A/E acting in owner's interests, with a historically strong bond, process
is well-established and understood -ANSWER-Design-Bid-Build (DBB)

Similar org structure to DBB, construction manager selected by QBS
or best value, contractor provides precon services, negotiated gmp
contracting approach, open book estimating process, potential to fast
track project, construction cost determined before design completed,
potential issues over what is reasonably inferable from gmp design
documents -ANSWER-construction manager at risk

The owner contracts with one entity (a person or firm) to provide both
design and construction services, designer and contractor have a
direct contractual relationship, selected by QBS or best value, wide

,spectrum of contracting approaches and organizational structures,
single point responsibility, owner does not manage designer, owner
exposure to claims is significantly reduced -ANSWER-Design-Build

Similar to design build, in industrial and power generation sectors,
systems and performance testing are central to scope, contractor will
typically perform engineering with its in-house staff, owner has need
for single point responsibility, contracts include plant and process
performance guarantees, contract items include performance and
schedule liquidated damages and limitations of liability -ANSWER-
engineer procure construct (epc)

Owner contracts with multiple trade contractors, attributes are typically
similar to dbb, owner's ability to schedule and coordinate the work -
ANSWER-Multiple Prime Contracting

Multi-party agreement - all parties equal, QBS procurement and target
pricing contract approach, private sector use (limited at this time), key:
owner's ability to accept risk -ANSWER-Integrated Project Delivery
(IPD)

Instead of government building and maintaining major infrastructure
(such as highway, water treatment plant), build and maintenance is
outsourced to a private company. Opposed by public sector unions.
This is not considered a delivery system but its underlying approaches
are delivery systems and typically use DB. Multiple procurement and
contracting approaches -ANSWER-public-private partnership (p3)

Intense efforts to establish scope early in the process; drives early
team formation to include key trade subcontractors; can enable big
decisions to be made early, affect project outcomes at lowest cost,

,establish a need for co-location and collaboration, and compress time
during concurrent design and construction -ANSWER-shift left

Typically two-phase best value procurement with lump sum contract;
owner defines project requirements and scope of prescriptive work;
use of performance-based technical requirements with limited
prescriptive specifications -ANSWER-traditional design build

Design and price are progressively developed after the design-builder
is under contract; final project cost and schedule commitment is not
established as part of the selection process; two phases: preliminary
services and final design and construction services -ANSWER-
progressive design build

Describe the end result -ANSWER-criteria documents

Prescribes how to achieve the end result -ANSWER-bridging
documents

Prior to bidding, owner undertakes a process to design the project and
all of its details to 100% complete plans and specs. The owner is
therefore responsible for success or failure of details of the design,
and warrants the sufficiency of design to the contractor. The owner is
therefore liable to the contractor for any gaps between plans and
specifications and owner's requirements for project performance -
ANSWER-design bid build paradigm

The owner should define its performance requirements and award the
contract on the basis of preliminary design; this makes the design-
builder responsible for completing the design in accordance with the
owner's performance requirements. That also causes the design-
builder to warrant the sufficiency of the design to meet the owner's

, criteria and the sufficiency of the design to subcontractors/suppliers
that have no design responsibility -ANSWER-design details
responsibility

Subdivides project by functional elements, focuses on systems and
assemblies, useful for preliminary information and early design
phases, aligns with BIM models and conceptual estimating -
ANSWER-uniformat

Subdivides work by results/trades, focuses on building materials,
products, and activities, useful for detailed information during final
design and construction phases, and aligns with detailed estimating -
ANSWER-masterformat

A specific business need or behavior as seen by an external user of
the system; describe what functions/operations the end product must
perform/accommodate; examples: regulatory, permitting, economic,
and others that define functions and operational capability. "Build an
office building on my existing lot to provide office space for 1,000
workers" -ANSWER-functional requirement

Describes what product(s) components must do/achieve with a
measurement metric; challenges: developing objective and definable
standards to validate performance, tendency to drift to prescriptive
specs; examples: uniformat C10, interior construction. "Provide
durable, paintable interior walls between the offices with STC 35
(min)" -ANSWER-performance requirement

Describes in terms of exactly how the product and/or its components
must be built; cookbook approach; developed by the design builder
but used by owners in the RFP/bridging documents for operability or
maintenance needs and conditions of permits or third parties;

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller paulynmugo. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $25.55. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73091 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$25.55
  • (0)
  Add to cart