What is the primary purpose of a punch list in construction?
- A) To document final payment details
- B) To outline additional work after project completion
- C) To list items needing correction before project completion
- D...
Construction & Evaluation: ARE 5.0
Questions and Answers 100% Pass
What is the primary purpose of a punch list in construction?
- A) To document final payment details
- B) To outline additional work after project completion
- C) To list items needing correction before project completion
- D) To schedule regular inspections
✔✔ C) To list items needing correction before project completion
Which document provides a detailed description of the materials and workmanship required for a
construction project?
- A) Project schedule
- B) Scope of work
- C) Specifications
- D) Construction contract
✔✔ C) Specifications
What is the main focus of a construction project’s evaluation phase?
1
,- A) Designing the project
- B) Monitoring construction progress
- C) Assessing project performance and quality
- D) Developing budget estimates
✔✔ C) Assessing project performance and quality
What does a construction change order typically address?
- A) Revisions to the original contract due to changes in scope
- B) Dispute resolutions between contractor and client
- C) New permits required for construction
- D) Final inspection results
✔✔ A) Revisions to the original contract due to changes in scope
What is the purpose of a construction submittal?
- A) To finalize project designs
- B) To obtain client approval for materials and methods
- C) To request additional funding
- D) To schedule inspections
2
,✔✔ B) To obtain client approval for materials and methods
What role does a contractor play in project evaluations?
- A) Designing the project
- B) Conducting final inspections
- C) Implementing the project and ensuring compliance with specifications
- D) Issuing building permits
✔✔ C) Implementing the project and ensuring compliance with specifications
What should be included in a project’s final inspection report?
- A) Design modifications
- B) Budget changes
- C) List of completed work and any deficiencies
- D) Schedule of upcoming tasks
✔✔ C) List of completed work and any deficiencies
Which document is used to track the performance and quality of work throughout the
construction phase?
3
, - A) Change order
- B) Daily log
- C) Project manual
- D) Building permit
✔✔ B) Daily log
What is typically the focus of post-construction evaluations?
- A) Reviewing initial project bids
- B) Analyzing client feedback and project outcomes
- C) Planning future projects
- D) Conducting preliminary design studies
✔✔ B) Analyzing client feedback and project outcomes
When should a contractor issue a notice of substantial completion?
- A) At the start of the project
- B) During the design phase
- C) When the project is substantially completed but not yet fully finished
- D) After receiving final payment
4
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller BrilliantScores. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.99. You're not tied to anything after your purchase.