Disagreements questions
with complete verified
solutions
Government Policy is to resolve all contractual issues in controversy
at what level? - answer With the Contracting Officer (technically the
lowest level possible, but the answer on exam is KO)
Protest - answer a written objection by an interested party to: a
solicitation, cancellation of solicitation, an award or proposed
award, termination or cancellation of an awar.
interested party - answer an actual or prospective offeror whose
direct economic interest would be affected by the award of a
contract or by the failure to award a contract
Protest Venues (3) - answer Government Accountability Office
(GAO), or the U.S. Court of Federal Claims, the agency
Agencies shall make their best efforts to resolve agency protests
within _________ days after the protest is filed. - answer 35 days.
When can an offeror file a protest (FAR 33.103(e))? Based on
solicitation impropriety - answer Before bid opening or receipt of
proposals