What should you do first before preforming duties in the proximity of overhead
power lines ? - correct answer ✔They must communicate with the power
company prior to starting the work and coordinate the activities that a
representative of the power company can be in attendance to assist while the
work is being performed
Electrical lines buried underground present the same potential for danger as
overhead lines - correct answer ✔True
Typical equipment you use for a overhead traffic signal installationand
maintenance? - correct answer ✔Typical equipment for above ground
includes bucket trucks plat form lift trucks boom trucks and cranes
When should a full body Harness be worn - correct answer ✔Whenever a
technician is on any type of aerial lift equipment
Where does the Full body harness straps around ? - correct answer ✔It
straps around the legs and shoulder of the technician and is tethered to the lift
arm of the aerial equipment
Workers must be aware of what? - correct answer ✔The location of utilities
that cannot be readily seen including what type they are and the potential for
danger that they possess.
The contractors should notify who before beginning excavation? - correct
answer ✔Notify all known utility owners prior to beginning excavation
,What is the most common underground utilities that might be encountered
doing construction for traffic signals? - correct answer ✔Gas and pressurized
water and sewer lines.
Workers are responsible not only for ensuring their own safety in the work
environment but also? - correct answer ✔Need to ensure that the traveling
public is safe
What is most commonly use besides traffic control plan ? - correct answer
✔Commonly known as maintenance of traffic plan
What's is MOT plan ? - correct answer ✔Maintenance of traffic plan
Workzone signs need to be done regardless of how short the activity. Is
expected to be. True or false - correct answer ✔True
Hazardous underground utilities:
Works must be aware of what ? - correct answer ✔Of the location of utilities
that cannot be readily seen, including what type they are and the potential for
danger that they possess.
Most states and provinces have established what ? - correct answer ✔Utility
protection laws that require contractors to notify all known utility owners prior
to the beginning excavation.
What is a MOT plan ? - correct answer ✔Maintenance of traffic plan
What is short duration maintenance or construction operations defined in the
MUTCD? - correct answer ✔An area for an hour or less at any time or
,daytime work that occupies a location for more than an hour with thin a single
day light period
Mobile operations ? - correct answer ✔Work activities that move along the
road either intermittently or continuously
What is a long term stationary? - correct answer ✔Work that occupies a
location more than 3 day
What is intermediate term stationary? - correct answer ✔1 daylight period up
to 3 days or nightime work lasting more than 1 hour
What is short term stationary? - correct answer ✔Daytime work that occupies
a location for more than 1 hour within a single daylight period.
What's is short duration operations? - correct answer ✔Work that occupies a
location up to 1 hour
What is a standard ? - correct answer ✔shall). A statement of required ,
mandatory
What is guidance ? - correct answer ✔should ) Recommend but not
mandatory
What is option? - correct answer ✔May ) Is a permissive condition
What is support ? - correct answer ✔An informational statement
, What is a negligence ? - correct answer ✔as the failure to do something that
a reasonable person would ordinarily do. Or do something that a reasonably
prudent person would not do.
What is a tort in legal terminology? - correct answer ✔Is a civil wrong
What is duty in tort law? - correct answer ✔An obligation requiring persons to
conform to a certain standard of conduct for the protection of others against
unreasonable risks.
What is a comparative negligence ? - correct answer ✔Of both parties is
compared and monetary recovery is permitted despite the contributory
negligence of the plaintiff
Contributory negligence is ? - correct answer ✔To conduct which falls below
the standard of care that a person is legally required to exercise for his own
safety and this failure is contributing cause to injury or damage that he
suffered
What does NEC stand for ? - correct answer ✔National Electrical Code
What does NESC stand for? - correct answer ✔National Electric Safety
Code
What did CEC stand for ? - correct answer ✔Canadian Electric Code
What are the color intervals during HAWK when a pedestrian crosses ? -
correct answer ✔(Flashing)CIRCULAR yellow signal,(Steady) CIRCULAR
yellow signal, followed by (Both Steady) CIRCULAR RED during the
pedestrian walk interval. Followed by alternating (flashing ) CIRCULAR RED
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller LEWISSHAWN55. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.