100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ISQS exam 4 Questions and Answers Verified by Expert 100% Correct $11.49   Add to cart

Exam (elaborations)

ISQS exam 4 Questions and Answers Verified by Expert 100% Correct

 5 views  0 purchase
  • Course
  • ISQS
  • Institution
  • ISQS

ISQS exam 4 Questions and Answers Verified by Expert 100% Correct

Preview 2 out of 12  pages

  • September 20, 2024
  • 12
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • ISQS
  • ISQS
avatar-seller
StudySet
ISQS exam 4 Questions and Answers Verified by
Expert 100% Correct 2024-2025
Choose the term characterized as a temporary and often-customized initiative
consisting of several smaller tasks and activities? It's necessary these tasks and
activities are coordinated and completed in order to finish the whole initiative by
its due date and within the allotted budget. - Project


Consider the stages of the project management life cycle. Of those stages, which
one incorporates responding to circumstances adversely impacting project
participants, managing alterations to baselines, as well as gathering and analyzing
status reports? - The controlling stage


Suppose you were to crash a project. Which statement below is most accurate
about your action? - it decreases the total duration of the project.


Consider an activity that normally takes 14 weeks to complete at a cost of $3,300.
The same activity can also be completed in 12 weeks at a cost of $4,000. What is
the crash cost per week for the activity described here? - $350


Which of the following are discrete tasks which require resources and time, within
the context of projects? - Activities


Which of the following dictates the duration of any project? - The longest path
through the project network


The district magistrate of Arkham City has decided to rebuild the busiest road in
the city. She plans to close the street for the duration of the work, causing

, immense inconvenience to the people who typically use the road. The project has
3 parallel paths defined as the following:
Path A-B-C-H will take 30 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 38 days.

Given the information on hand, which of the following statements is true? -
Path A-F-G-H is the critical path.


Tammy, leads the advertising of an innovative product, Teckos, just launched by
her company. She has determined the advertising for Teckos is an individual
project consisting of 7 activities. Information pertinent to these activities is
included in the table that follows.
ActivityImmediate Predecessor(s)Activity Time(in
weeks)ANone2BNone2CA4DB5EC5FD1GE, F2


Using a Gantt chart, determine the late start of Activity E. - 6


Seven activities are to be considered for this problem. Additional information
about these activities such as their activity time and immediate predecessors are
included in the table that follows. Use this information to figure out the earliest
completion time (earliest finish) for this project using a Gantt or network chart.
ActivityImmediate Predecessor(s)Activity Time(in weeks)ANone3BA1CA4DB5EB,
C5FC1GD, E, F4 - 16 weeks


Seven activities are to be considered for this problem. Additional information
about these activities such as their activity time and immediate predecessors are
included in the table that follows. Use this information to figure out the slack time
for activity E.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller StudySet. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $11.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

72042 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$11.49
  • (0)
  Add to cart