100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PE Professional Engineer Exam Construction With Correct Questions And Answers 2024 $15.49   Add to cart

Exam (elaborations)

PE Professional Engineer Exam Construction With Correct Questions And Answers 2024

 3 views  0 purchase
  • Course
  • PE Professional Engineer
  • Institution
  • PE Professional Engineer

PE Professional Engineer Exam Construction With Correct Questions And Answers 2024

Preview 3 out of 19  pages

  • September 23, 2024
  • 19
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • types of loads
  • wood framing
  • PE Professional Engineer
  • PE Professional Engineer
avatar-seller
RANKGRADES
PE Professional Engineer Exam
Construction With Correct Questions And
Answers 2024


Types .of .Loads .- .correct .answer.Dead, .Live, .Construction, .Environmental, .and .Lateral
.Earth .Pressure




Available .Design .Methods .for .Construction .Loads .- .correct .answer.Allowable .Stress
.Design .(ASD)

Load .and .Resistance .Factor .Design .(LRFD)

Building .Type .& .Construction .Method .- .correct .answer.Residential: .Light .wood .stick
.framing

Commercial: .Wood, .steel, .or .masonry
High-rise .and .other .commercial: .heavy .steel .framing .or .reinforced .concrete
Long-Span .Bridges: .steel .cables

Wood .Framing .- .correct .answer.Most .common .way .to .build .houses .in .NA

Simplified .Building .Procedure .for .Wood .House .- .correct .answer.1. .Place .concrete
.foundation

2. .Place .first .floor .walls
3. .Construct .wood .platform .to .build .second .floor
4. .Place .second .floor .walls
5. .Place .roof .on .top .of .2nd .floor .walls

Steel .Framing .- .correct .answer.Most .common .for .high-rise .and .commercial .buildings
Similar .to .wood .but .with .less .flexibility
High .strength .& .relatively .light .weight
Expensive .compared .to .other .materials

Concrete .Structures .- .correct .answer.Concrete .systems .are .commonly .used .in .high-ride
.buildings

More .resistant .to .fire .than .steel .or .wood

,Less .prone .to .corrosion .than .steel .(common .for .UG .structures)

Simplified .Building .Procedure .for .Concrete .Structures .- .correct .answer.1. .Prepare
.concrete .mix .design

2. .Prepare .formwork
3. .Pour .steel .reinforcement
4. .Pour .Concrete
5. .Allow .for .concrete .curing .process
6. .Disassemble .formwork

Advantage .of .Precast .Concrete .- .correct .answer.Higher .quality .fabrication .from .casting
.off-site

Can .accelerate .construction .schedules

A .two-story .multi-family .residential .structure .is .being .construction .in .a .high .seismic .area.
.Which .construction .type .is .most .likely .to .be .used? .- .correct .answer.Wood .Framing

(2-story, .low .rise .residential) .
"High-seismic" .is .a .distractor

Temporary .Structures .- .correct .answer.May .be .removed .at .end .of .construction .(usually)
May .be .incorporated .into .the .finished .structure
Concrete .formwork .is .a .common .example .of .temporary .structure

Design .Considerations .of .Concrete .formwork .- .correct .answer.Dead .Load: .weight .of
.fresh .concrete .plus .form .self .weight

Live .Load: .50-75 .psf .depending .on .equipment .used .(to .pour .concrete)
Lateral .pressure .exerted .by .fresh .concrete

Typical .formwork .material .- .correct .answer.3/4" .plywood .that .is .coated .on .one .side

Types .of .concrete .formwork .- .correct .answer.Slab .Formwork
Beam .Formwork
Column/Wall .Formwork .(look .at .photos)

Equation .for .Lateral .Pressures .of .Concrete .- .correct .answer.ACI .347R-14 .Table
.4.2.2.1a(a)




Project .Management .Process .Groups .- .correct .answer.Initiation .-> .Planning .-> .executing
.-> .Controlling .and .monitoring .(loop .back .to .planning) .-> .closing

Ex. .of .loop .(Value .Engineering)

Gantt .Chart .- .correct .answer.Small .to .mid-size .projects
Forecast .& .manage .resources .(labor, .equipment, .budgets, .etc)
Disadvantage: .doesn't .show .all .the .links/sequencing

, Critical .Path .Method .(CPM) .- .correct .answer.Project .modeling .technique .that .identifies
.the .most .critical .activities .on .a .schedule

Helps .monitor .the .assets, .expenses, .and .advancement .of .the .project
Activity .on .Node .(AON) .is .most .common

PERT .- .correct .answer.Program .Evaluation .Review .Technique .(also .known .as .CPM)

Float .Time .(slack .time) .- .correct .answer.Amount .of .time .that .an .activities .can .be .delayed
.without .affecting .the .overall .schedule .(applies .to .activities .not .on .CP)




Applying .the .CPM .(steps) .- .correct .answer.1. .Specify .each .activity
2. .Sequence .the .activities
3. .Draw .the .network .diagram
4. .Identify .the .CP
5. .Update .to .show .progress

AOA .(Activity .on .Arc) .
Define .Dummy .Nodes .& .Dummy .Activities .- .correct .answer.Dummy .Node: .Used .when .2
.activities .have .the .same .starting .and .ending .event

Dummy .Activity: .Have .no .duration, .used .to .prevent .an .activity .from .occurring .in .more
.than .2 .spot




Contract .Documents .(what .is .included?) .- .correct .answer.Contract .Terms
Quantity .and .cost .estimates
project .and .task .descriptions .(SOW)
Specification .of .the .deliverables
Time, .resources, .and .payment

Design .Sequencing .Phases .- .correct .answer.Schematic .Design
Design .Development
Construction .Documents
Bidding .Process

Project .Costs .- .correct .answer.Direct .Costs .(Raw .materials, .labor, .fuel, .etc)
Indirect .Costs .(Overhead, .taxes, .administrative)

Find .the .correct .sequence .for .a .building .foundation
i. .Site .clearing
ii. .Installing .sewers .& .other .utilities
iii. .Excavation .for .utility .trenches
iv. .Grading .general .area
v. .Formwork .and .reinforcement
vi. .Pour .concrete .- .correct .answer.i,iv,iii,v,ii,vi

Assumptions .for .Engineering .Economics .Problems .- .correct .answer.Inflation .is .0%
.through .lifetime .of .project

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller RANKGRADES. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $15.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81989 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$15.49
  • (0)
  Add to cart