Comprehensive HVAC Cx - New Construction: Design Phase Key Activities
- Correect any deficiencies, and carry out any required re-testing
- Carry out any required "off-season" tests
- Update documentation as required
- Carry out FPTs on all HVAC systems
- Train the O&M staff for effective, ongoing operations and maintenance of all systems
- Provide full documentation
- Review design to ensure it accommodates Cx
- Write commissioning specifications defining contractor responsibilities
- CxA writes the Cx plan
- Establish the project schedule
- CxA reviews contractor submittals
- CxA updates Cx plan
- Cx process is coordinated - through project schedule, Cx plan, and Cx meetings
- Carry out and document system verification checks
- Carry out the document equipment and system start-ups
- TAB agency completes and documents test and balance work
,Term 2 of 27
Comprehensive HVAC Cx - New Construction: Post-Acceptance Phase Key Activities
- CxA reviews contractor submittals
- CxA updates Cx plan
- Cx process is coordinated - through project schedule, Cx plan, and Cx meetings
- Carry out and document system verification checks
- Carry out the document equipment and system start-ups
- TAB agency completes and documents test and balance work
- Correect any deficiencies, and carry out any required re-testing
- Carry out any required "off-season" tests
- Update documentation as required
- Review design to ensure it accommodates Cx
- Write commissioning specifications defining contractor responsibilities
- CxA writes the Cx plan
- Establish the project schedule
- Carry out FPTs on all HVAC systems
- Train the O&M staff for effective, ongoing operations and maintenance of all systems
- Provide full documentation
,Term 3 of 27
Who does Commissioning benefit most?
Cx Authority is an independent, third party that works for the owner and serves the
owner's best interest by delivering a facility with systems that perform as specified,
intended, and paid for
Most benefits continue for the life of the building
Term 4 of 27
What does AABC Stand for and when was it started?
A quality assurance approach resulting in significant value to the owner
Between 2% and 5% of the HVAC construction cost
Approx. 80% of that for Comprehensive Cx
Associated Air Balance Council - 2002
, Term 5 of 27
Construction HVAC Cx : Acceptance Phase Key Activities
- Carry out FPTs on all HVAC systems
- Train the O&M staff for effective, ongoing operations and maintenance of all systems
- Provide full documentation
- Carry out and document FPTs
- Verify reported TAB results
- Train O&M staff
- Submit final Cx report
- Identify Cx scope; develop Cx test details
- CxA reviews contractor submittals
- Coordinate Cx process - through Cx plan, Cx meeting and schedule
- Carry out and document system verification checks
- Observe and document equipment and system start-ups
- TAB agency completes and documents test and balance work
- Carry out and document any required "off season" FPTs
- Revise and submit final Cx report, if required
Term 6 of 27
What is Commissioning?
Independent certified Cx Authority under direct contract to the owner.
A 3rd party professional brings objectivity and practical experience to the project to
provide a consistent level of assurance that the owner's best interest's will be served
A systematic process that facilitates and ensures the required communication,
coordination, testing, and verification, and results in the delivery of a building whose
HVAC systems perform as intended.
A quality assurance approach resulting in significant value to the owner
Associated Air Balance Council - 2002
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller selftest. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $7.99. You're not tied to anything after your purchase.