Where is the best location for leveling a crane? - ANSWER✔✔Upperworks
When determining the "gross load" the best method is: - ANSWER✔✔Get an
accurate load weight and add the rigging.
By order of hitch strength, which is the correct answer? - ANSWER✔✔Basket,
vertical, choker
What is the purpose of using a jib? - ANSWER✔✔Increase height
When taking a side strain on a boom, what concerns the operator most? -
ANSWER✔✔Boom damage
You should always have at least how many wraps on a hoist drum? -
ANSWER✔✔2
On a load chart, values above the bold line mean: - ANSWER✔✔Capacities based
on structural competence.
The primary purpose for a rooster sheave or Auxiliary boom point is to: -
ANSWER✔✔Separate the hoist lines.
What is the proper procedure when using an insulating link or a boot near power
lines? - ANSWER✔✔Be sure to maintain the correct allowable distance from the
lines.
When the number of layers of rope on a drum increases, the: -
ANSWER✔✔Allowable line pull decreases.
What is the minimum allowable distance from the crane and power lines under
50kV? - ANSWER✔✔10 ft.
, The term "Upperworks or Superstructure" refer to the area of the crane: -
ANSWER✔✔Above the turntable
Side loading may be caused by: - ANSWER✔✔Starting or stopping the swing too
rapidly.
What is the best procedure to follow when underground utilities may be present?
- ANSWER✔✔Contact local utility company
Eccentric main boom tip reeving causes: - ANSWER✔✔Twisting of the boom
How many randomly broken wires must there be to remove a running wire rope
from service? - ANSWER✔✔6
When lifting personnel in a man-basket using 6x19 wire rope, the minimum safety
factor is? - ANSWER✔✔7
What is the safety factor required when using non rotating wire rope and lifting
personnel in a man-basket? - ANSWER✔✔10
Who has the responsibility for determining the correct weight of a load? -
ANSWER✔✔Supervisor
When working near power lines, when is a signal person required? -
ANSWER✔✔When crane moves within a boom's length of power lines.
When an operator leaves the crane, he must first: - ANSWER✔✔Put the load on
the ground and put all dogs or pawls in.
If replacing the hoist line wire rope on a crane, how do you determine the size of
type of wire rope to use? - ANSWER✔✔Use Manufacturer's operators manual or
load chart.
After the crane has been checked out and before crane lift operations begin, the
crew should: - ANSWER✔✔Have a pre-lift meeting
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller classhub. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.99. You're not tied to anything after your purchase.