SAFe RTE 6.0 Exam Graded A+ 2024
A Coach Sync occurs just before the draft plan review during PI Planning. The Scrum
Master/Team Coach (SM/TC) from one team raises an issue that Product Management
just showed up to the planning area with a list of priority work. This work does not align
with the Feature prioritization. What is the most likely planning and anti-pattern causing
this sudden impediment? - ANSWER-Prioritization by Product Management was
performed autonomously not collaboratively
A Release Train Engineer (RTE) primarily establishes a relationship with which role? -
ANSWER-System Architect (and Product Management)
A Release Train Engineer (RTE) wants to try a new retrospective technique at the next
Inspect and Adapt (I&A) event. However, the RTE is unsure how to prepare and thinks
there may be some pitfalls. How can the RTE get help? - ANSWER-Share and receive
feedback from other RTEs in a community of practice
After an ART's first PI Planning, what action can the Release Train Engineer (RTE) take
to help optimize the ART Backlog readiness for the next PI? - ANSWER-Coach Product
Management and the System Architect to include ART Backlog refinement into their
cadence-based approach
At which stage will the ART act as a one-team culture? - ANSWER-Creating a flow of
knowledge across the teams and ART, known as performing
At which stage will the ART act as a one-team culture? - ANSWER-Creating a flow of
knowledge across the teams and ART, known as performing
At which Tuckman stage would an ART be if it improves engineering practices and
fosters more effective communication? - ANSWER-Norming
Business Owners are frequently unhappy with Solutions presented in the System
Demos. What action can a Release Train Engineer (RTE) take to help resolve this
issue? - ANSWER-Include the Business Owners in the PO Sync
During PI execution, the team needs clarification about how to test some of the larger
Features. How can the RTE help the team? - ANSWER-Encourage the Team and
Product Management to meet and collaborate on a Solution
During the storming stage of ART development and evolution, in which area should a
Release Train Engineer (RTE) mentor Scrum Masters/Team Coaches (SM/TC)? -
ANSWER-Conflict resolution techniques
, During which part of an Inspect & Adapt (I&A) event are differences between planned
business value and actual business value presented? - ANSWER-Quantitative and
qualitative measurement
Establishing ART Flow measures falls under which Release Train Engineer (RTE)
responsibility? - ANSWER-Optimizing flow
How does a Release Train Engineer (RTE) view the role of functional managers on the
ART? - ANSWER-Developer of people
In what way is a Value Stream map different from a process flow? - ANSWER-It
measures the flow of value and identifies bottlenecks for improvement
Teams report high success through their individual quantitative measurements, but the
system results do not support the teams' reports. What should the Release Train
Engineer (RTE) do to help the teams deliver more value? - ANSWER-Coach the Scrum
Master/Team Coach (SM/TC) on good retrospective techniques and ensure teams are
defining and taking a systems view approach to improvements
To evolve the role of a leader in SAFe, which practices can the Release Train Engineer
(RTE) recommend? - ANSWER-Encourage personal development
What action can reduce team collaboration during the PI Planning event? - ANSWER-
Overpreparing for PI Planning
What action should the ART take when the Release Train Engineer (RTE) cannot
facilitate PI Planning due to unexpected circumstances? - ANSWER-Leverage the
person who worked closest with the RTE during the preparation sessions as a
replacement facilitator
What activity occurs during the first team breakout during PI Planning? - ANSWER-All
teams planning boards are visible and used the same color-coding
What can the Release Train Engineer (RTE) do to ensure key PI Planning preparation
activities are remembered and are part of multiple ART roles? - ANSWER-Arrange
regular preparation meetings during the PI; use the ART readiness workbook and ask
who would like to drive which action lines
What is an outcome of the team's draft plan review at the end of the first day of PI
Planning? - ANSWER-Risks and impediments
What is one action done immediately during the management review and problem-
solving meeting? - ANSWER-Change the scope
What is one action the Release Train Engineer (RTE) can take to facilitate team
growth? - ANSWER-Encourage continuous learning
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller CLOUND. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.99. You're not tied to anything after your purchase.