1. In which project management process group
is the detailed project budget created?
A. Initiating
B. Before the project management process
C. Planning
D. Executing - ANSWER Answer C
Notice the use of the word 'detailed'. Such a budget
is created during the planning process group.
2. T...
PMP Rita Exam Prep Questions - Chapter 3
Project Mgmt Processes CORRECT 100%
1. In which project management process group
is the detailed project budget created?
A. Initiating
B. Before the project management process
C. Planning
D. Executing - ANSWER Answer C
Notice the use of the word 'detailed'. Such a budget
is created during the planning process group.
2. The project charter is created in which project management process group?
A. Executing
B. Planning
C. Closing
D. Initiating - ANSWER Answer D
The project charter is needed before planning and execution of the work can begin.
3. The project team has just completed the initial project schedule and budget. The NEXT thing to do is:
A. Identify risks
B. Begin iterations
C. Determine communications requirements
D. Create a bar (Gantt) chart - ANSWER Answer C
, Communications requirements and quality standards are needed before risks (especially risks relating to
communications and quality) can be determined (choice A). Iterations (choice B) cannot begin until the
risks are identified, qualified, quantified, and responses developed.
These then create the need to revise the WBS and other parts of the project management plan.
A bar chart (choice D) would have been done during the creation of the schedule, so it cannot be the
next thing. Of the choices listed, determine communications requirements (choice C) is the best.
4. A detailed project schedule can be created only after creating the:
A. Project budget
B. Work breakdown structure
C. Project management plan
D. Detailed risk assessment - ANSWER Answer B
In the project management process, the project budget (choice A), project management plan (choice C),
and detailed risk assessment (choice D) come after the schedule. The only answer that could be an input
is the WBS.
5. The person who should be in control of the project during project planning is the:
A. Project manager
B. Team member
C. Functional manager
D. Sponsor - ANSWER Answer A
The project manager should be named early in the project, during project initiating if possible.
6. Which of the following is NOT an input to the initiating process group?
A. Company processes
B. Company culture
C. Historical WBSs
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Lecchris. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.99. You're not tied to anything after your purchase.