HSI Final Test UPDATED ACTUAL Questions and CORRECT Answers The initial response to a frequency deviation is due to which of the following 1. Load / frequency response 2. AGC 3. Governor action 4. Interchange schedules •3 and 4 •1 and 2 •2 and 3 •1 and 3 - CORRECT ANSWER- •1 a...

[Show more]

Preview 3 out of 28  pages

  • October 15, 2024
  • 28
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • HSI
  • HSI
avatar-seller
MGRADES
HSI Final Test UPDATED ACTUAL
Questions and CORRECT Answers
The initial response to a frequency deviation is due to which of the following
1. Load / frequency response
2. AGC
3. Governor action
4. Interchange schedules


•3 and 4
•1 and 2
•2 and 3

•1 and 3 - CORRECT ANSWER✔✔- •1 and 3


EMS and AGC have failed at 12:25 and generation must be controlled manually. The operator
calculates ACE to be +25 MWs. Load is expected to increase 100 MWs, and imports will
increase by 75 MWs at the top of the hour. What should the operator do?


•Maintain current generation level
•Decrease generation by 25 MWs
•Decrease generation by 50 MWs

•Increase generation by 25 MW - CORRECT ANSWER✔✔- •Decrease generation by 25
MWs


How is the Frequency Response Measure (FRM) of a Balancing Authority determined?


•lt is the average of the BA's frequency response for all the frequency deviations of the
previous year
•lt is the change in the BA's Net Interchange Actual for the largest frequency deviation during
the previous year
•lt is the previous year's Control Performance Standard 1 ( CPS1 ) score

,•It is the median of the BA's frequency response for the frequency deviation events identified
by NERC for the previous year - CORRECT ANSWER✔✔- •It is the median of the BA's
frequency response for the frequency deviation events identified by NERC for the previous
year


Sufficient Operating Reserve is defined as the capacity required to meet what?


•DOE specifications
•CPS and DCS
•CPS 1 & 2 only

•Capacity Standard - CORRECT ANSWER✔✔- •CPS and DCS


In your Interconnection , a generator tripped that was large enough to reduce the frequency
from 60.00 Hz to 59.94 Hz . Your Balancing Authority's Frequency Bias is -200 MW / 0.1 Hz
. How many MW would your system initially contribute to frequency support?


•120 MW
•80 MW
•100 MW

•200 MW - CORRECT ANSWER✔✔- •120 MW


Interconnection frequency is 59.80 Hz . Your ACE is a large negative value and your AGC is
pulsing your units down . What should you do


•Leave AGC in operation but investigate
•Place AGC in constant frequency control
•Place AGC in flat tie line control

•Suspend AGC and investigate - CORRECT ANSWER✔✔- •Suspend AGC and investigate


When a Balancing Authority's ACE value is the same sign as the frequency deviation , which
NERC control performance score is affected negatively

, •DCS
•CPS 1
•TEC

•BAAL - CORRECT ANSWER✔✔- •CPS 1


Correct Of the following , which control system would be affected by a difference in Net
Actual Interchange and Net Scheduled Interchange


•Reactive Control
•Turbine Governor Control
•Automatic Generation Control

•Automatic Voltage Regulator - CORRECT ANSWER✔✔- •Automatic Generation Control


Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its Net Actual
Interchange is +100 MW and its Net Scheduled Interchange is +100 MW . If Balancing
Authority A's frequency bias setting is 100 MW / 0.1 HZ , what is ACE


• -20
•20
•2

•0 - CORRECT ANSWER✔✔- • -20


A Balancing Authority has twenty units on governor control . The units have different
capacities that range from 200 MW to 1000 MW and droop settings from 2 % to 5 % . The
biggest adjustments in megawatt output in response to a frequency disturbance will be
provided by units that have _______________?


•large capacity and small droop setting
•large capacity and large droop setting
•small capacity and small droop setting

•small capacity and large droop setting - CORRECT ANSWER✔✔- •large capacity and
small droop setting

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller MGRADES. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $9.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

80461 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$9.99
  • (0)
  Add to cart