law set into place in 1970 for storm water regulat
regulations for monitoring storm water activity on
when should you read and understand swpp
Institution
QSD - Qualified SWPPP Designer
Course
QSD - Qualified SWPPP Designer
$14.49
100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached
SWPPP Study Guide Questions With Real
Answers 2024
Law .set .into .place .in .1970 .for .storm .water .regulation .- .correct .answer.Clean .Water .Act
Regulations .for .monitoring .storm .water .activity .on .a .construction .site, .are .outlined .in .-
.correct .answer.NPDES
When .should .you .read .and .understand .SWPP .- .correct .answer.Immediately .after .project
.is .awarded .and .before .you .begin .any .site .work
What .is .not .an .allowable .storm .water .discharge .or .non-storm .water .discharge .- .correct
.answer.Contaminated .ground .water
When .may .construction .activity .begin .- .correct .answer.When .jurisdiction .of .operations
.specifies .you .can .start
Waters .that .fail .anti-degradation .list .are .placed .on .which .list. .- .correct .answer.303D .list
SWPPPs .certification .are .signed .by .who .- .correct .answer.An .officer .and .project .owner
The .document .that .must .be .completed .signed .and .submitted .to .the .state .to .obtain
.authorization .to .discharge .is .the .NOT. .(T/F) .- .correct .answer.FALSE
NOT .can .be .filed .when .- .correct .answer.All .construction .has .been .completed .both .inside
.and .outside
Operations .on .a .construction .site .are .the .entity .in .charge .of .plans .and .specification .and
.the .entity .who? .- .correct .answer.is .in .charge .of .daily .activities
Motives .for .staying .in .compliance .with .storm .water .objectives? .- .correct .answer.Stay .out
.of .trouble .with .the .law
Objectives .of .the .clean .water .act .are .- .correct .answer.To .protect .and .preserve .beneficial
.use .of .U.S. .waters, .maintaining .their .clean, .physical .and .biological .integrity
NPDES .stands .for .- .correct .answer.National .Pollutant .Discharge .Elimination .System
, Which .are .a .component .of .a .good .SWPPP .- .correct .answer.Site .description .and .maps,
.inspection .and .maintenance .procedure. .Potential .pollutant .sources, .schedules .of
.activities, .site .contact .information, .plan .certification .documents, .site .contact .info .and
.descriptions .of .controls .BMP
Construction .sediment .is .not .considered .a .potential .pollutant .source .(T/F) .- .correct
.answer.False
When .modifying .or .substituting .a .storm .water .BMP .the .contractor .must .consult .with .-
.correct .answer.Project .owner, .SWPPP .designer
NOI .must .be .submitted .to .the .appropriate .agency .before .the .storm .water .pollution
.preventive .plan .is .developed .(T/F) .- .correct .answer.False
Name .of .the .list .with .impaired .waters .is .called .totally .daily .maximum .load .(T/F) .- .correct
.answer.False, .303d .List
You .should .have .a .SWPPP .for .your .construction .site .because? .- .correct .answer.It .is
.required .by .law, .it .documents .storm .water .management .activity .on .your .site, .and .it
.demonstrates .your .intent .to .manage .storm .water .on .your .site
A .well .constructed .SWPPP .for .your .site .should .be? .- .correct .answer.Site .specific
The .NOI .must .be .submitted .when? .- .correct .answer.Prior .to .commencing .construction
One .necessary .component .of .a .good .SWPPP .is? .- .correct .answer.Schedule .of .activities
Factors .that .may .impact .SWPPP .scheduling .activities .include .- .correct .answer.Weather
.and .Climate
Pollutant .sources .on .a .construction .may .include .- .correct .answer.masonry .materials,
.petroleum .storage .tanks, .soil .amendments .fertilizer, .lime .etc
If .you .believe .BMP .modification .are .necessary .to .the .site .you .must? .- .correct
.answer.Seek .written .approval .of .the .project .SWPPP .designer .or .project .owner
The .following .consideration .may .be .incorporated .into .the .SWPPP? .- .correct
.answer.Endangered .species .and .historical .preservation
The .SWPPP .will .contain .the .following? .- .correct .answer.Site .maps, .erosion .sediment
.control, .BMPs, .site .specific .sequences .of .construction .activities
Once .the .site .has .experienced .rain .event .of .measurable .quantity .you .must? .- .correct
.answer.Identify .deficient .and .failed .BMPs .and .make .repairs .immediately