& ANSWERS(RATED A)
The right to repossess or replevy unused materials from a jobsite will not be effective if someone, in
good faith, purchased it after removal from the site of the improvement. - ANSWER True.
The contractor must within _____ days after the receipt of the property owner's request, furnishish to
property owner or the property owner's agent a list of the subcontractors and suppliers who have a
contract with the contractor as of the date the request is received by the contractor. - ANSWER 10 days.
A property perfected lien may be discharged by an order of the circuit court of the _____ where the
property is located. - ANSWER county
When any interested party files a complaint, the clerk will issue a summons to the lienor to show cause
within _____ days why his or her lien should not to be enforced by action or vacated and canceled of
record. - ANSWER 20 days
If a lienor fails to show cause why his or her lien should not be enforced or fails to start such action
before the return date of the summons, the court will immediately order cancellation of the lien. -
ANSWER True
No lien provided by part 713.22 will continue for longer then ____ years after the claim of lien has been
recorded. - ANSWER 1 year
No lien provided by part 713.22 will continue for no longer then _______ years after the recording of an
amended claim of lien that shows a later date of final furnishing of labor, services, or materials. -
ANSWER 1 year
The lien of any lienor upon whom Notice of contest of Lien is served and who fails to institute a suit to
enforce his or her lien within ________ days after service of such notice will be extinguished
automatically. - ANSWER 60
, The payment bond is required to ______ an owner under s. 713.23 must be furnished by the contractor
in at least the amount of the original contract price before commencing the construction of the
improvement under the direct contract. - ANSWER exempt
A copy the payment bond must be attached to the Notice of Commencement when it is _______. -
ANSWER recorded
Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the ______ degree -
ANSWER third
When a construction project is "put out" for bid, the contractors are given the plans and specifications
for the project. If any deviations for these specifications occur, who will be held responsible and may be
required to correct them at their own expense? - ANSWER The contractor
The ______ for a protect are interpreted as a legal document that specifically defines the responsibilities
of the owner and his representatives intended for the project and what the contractors responsibilities
are. - ANSWER specifications
The CSI-MASTERFORMAT divides the specifications into __________ specific divisions to provide a
standard reference and filing numbers for bidding and contract forms. - ANSWER 50
Which of the following would appear as a heading in the index of the General Clauses and Conditions
sections of General Requirements? - ANSWER All of these ( General Conditions, Notice to Bidders and
Proposal)
_________ is the contractors price for performing the work as specified. - ANSWER The proposal
"Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items that would be
included under what heading in the General Clauses and Conditions section? - ANSWER General
Conditions
The square footage method of estimating is always recommended for lump-sum contracts. - ANSWER
False